802 S WESTHOLME AVE 90024
Certificate Information: 802 S WESTHOLME AVE 90024
- Application / Permit
- 23016-10000-09865
- Plan Check / Job No.
- B23LA06003
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN- REMODEL SFD/GARAGE. ADD EXT DOOR AT GARAGE. Remodel (3) bdrms and (3) bthrms. ALL WORK PER ENGINEERY.
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- Issued on 1/18/2024
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/15/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/6/2023 | ANGELICA MARTINEZ |
| Issued | 1/18/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/12/2023 | BRIAN MILLER |
Contact Information
| Architect | Eckelberry,, Anthony Evans; Lic. No.: C17278 | 4535 GAINSBOROUGH AVE. LOS ANGELES, CA 90027 |
| Contractor | Curtis Construction Services; Lic. No.: 974084-B | , |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: NA78194 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 4/8/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 4/10/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/10/2024 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 4/16/2024 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/18/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 4/18/2024 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 4/22/2024 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 4/22/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/22/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/25/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/25/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 4/25/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/2/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 5/2/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 5/6/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/6/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 5/6/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/15/2024 | Approved | STEPHANIE SWANSON |