100 WORLD WAY 90045

Certificate Information: 100 WORLD WAY 90045

Application / Permit
23016-10000-09553
Plan Check / Job No.
B23LA05900
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
**ePlan**LAX** Install (3) antennas, (4) RRUs and (2) diplexers at rooftop; install cables to and from existing IDF Room to equipment on rooftop
Permit Issued
Issued on 12/18/2023
Issuing Office
Current Status
Permit Finaled on 12/16/2025

Permit Application Status History

Submitted 4/3/2023 APPLICANT
Assigned to Plan Check Engineer 4/26/2023 FARSHAD ALIMOHAMADI
Corrections Issued 5/2/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 5/8/2023 CHARLES CHANG
Applicant returned to address corrections 6/11/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 6/26/2023 FARSHAD ALIMOHAMADI
Issued 12/18/2023 APPLICANT
Permit Finaled 12/16/2025 NICK LAROCCA

Permit Application Clearance Information

DAS Clearance Cleared 5/3/2023 Lily Teng
Project Permit Cleared 5/30/2023 FARSHAD ALIMOHAMADI
City owned building/parcel Cleared 6/20/2023 FARSHAD ALIMOHAMADI

Contact Information

Contractor Aztecs Telecom Inc; Lic. No.: 890747-B       ,
Engineer Badral,, Zoljargal; Lic. No.: C90657 401 S KINGSLEY DR APT 326      LOS ANGELES, CA 90020

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Fireproofing 4/23/2024 Conditional Approval ALAN NOVAK
Deputy Fireproofing 4/24/2024 Conditional Approval ALAN NOVAK
Deputy Fireproofing 4/25/2024 Conditional Approval ALAN NOVAK
Deputy Fireproofing 4/26/2024 Conditional Approval ALAN NOVAK
Deputy Fireproofing 4/29/2024 Conditional Approval ALAN NOVAK
Final 10/20/2025 No Access for Inspection NICK LAROCCA
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Approved NICK LAROCCA
Smoke Detectors 10/20/2025 Approved NICK LAROCCA
Final 10/21/2025 Not Ready for Inspection NICK LAROCCA
Final 12/16/2025 Permit Finaled NICK LAROCCA