1026 N HUDSON AVE 90038

Certificate Information: 1026 N HUDSON AVE 90038

Application / Permit
23016-10000-09544
Plan Check / Job No.
B23LA05892
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SSR Retrofit using (1) Ordinary Moment Frame and (3) Special Steel Cantilever Columns
Permit Issued
Issued on 5/31/2023
Issuing Office
Current Status
CofC Issued on 11/9/2023

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 HANS SANTIAGO
Corrections Issued 4/10/2023 HANS SANTIAGO
Quality Review Completed 4/12/2023 CHARLES CHANG
Plan Check Approved 4/26/2023 ANDREW SANTIAGO
Issued 5/31/2023 APPLICANT
OK for CofC 11/3/2023 JACOB MYERS
CofC Issued 11/9/2023 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 5/25/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Biayna Engineering & Construction; Lic. No.: 998853-B 9751 WHEATLAND AVE      SUNLAND, CA 91040
Engineer Muradyan,, David; Lic. No.: NA6232       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 6/29/2023 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 7/20/2023 Approved VAHE KELEDJIAN
Deputy Reinf. Concrete 7/21/2023 Order to Comply Issued VAHE KELEDJIAN
Structural Steel Frame 7/21/2023 Partial Inspection VAHE KELEDJIAN
Wood Frame 7/21/2023 Corrections Issued VAHE KELEDJIAN
Structural Steel Frame 10/4/2023 Conditional Approval VAHE KELEDJIAN
Wood Frame 10/4/2023 Conditional Approval VAHE KELEDJIAN
Interior/Exterior Lathing 10/20/2023 Conditional Approval VAHE KELEDJIAN
Final 11/3/2023 OK for CofC JACOB MYERS
METHANE-Final 11/3/2023 Approved JACOB MYERS
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved JACOB MYERS
Smoke Detectors 11/3/2023 Approved JACOB MYERS