1449 S POINT VIEW ST 90035
Certificate Information: 1449 S POINT VIEW ST 90035
- Application / Permit
- 23016-10000-09346
- Plan Check / Job No.
- B23LA05752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Retrofit with (1) 2 way Special Steel cantilever column and wood shear wall. *1 Parking reduction due to retrofit obtained under permit 23016-10000-15680*
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofC Issued on 3/27/2025
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | HANS SANTIAGO |
| Corrections Issued | 4/17/2023 | HANS SANTIAGO |
| Quality Review Completed | 4/17/2023 | CHARLES CHANG |
| Applicant returned to address corrections | 5/15/2023 | HANS SANTIAGO |
| Plan Check Approved | 6/21/2023 | ANDREW SANTIAGO |
| Issued | 6/27/2023 | APPLICANT |
| OK for CofC | 9/18/2023 | RONALD JIMENEZ |
| CofC Issued | 3/27/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/27/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Courteous Construction Co Inc; Lic. No.: 567324-B | P O BOX 9287 GLENDALE, CA 91226 |
| Engineer | Rezazadeh,, Mehdi; Lic. No.: C49626 | P O BOX 98 DANVILLE, CA 94526 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/25/2023 | Corrections Issued | DARRYL ARNOLD |
| Deputy Steel/Welding | 8/3/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 8/4/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/4/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/8/2023 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 8/8/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/8/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/10/2023 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 8/10/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/29/2023 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/1/2023 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/6/2023 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/8/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 9/15/2023 | Partial Inspection | RONALD JIMENEZ |
| METHANE-Final | 9/15/2023 | Partial Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 9/15/2023 | Approved | RONALD JIMENEZ |
| Final | 9/18/2023 | OK for CofC | RONALD JIMENEZ |
| METHANE-Final | 9/18/2023 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 7/2/2024 | Corrections Issued | DARRYL ARNOLD |