4466 S HARDING AVE 90066
Certificate Information: 4466 S HARDING AVE 90066
- Application / Permit
- 23016-10000-09325
- Plan Check / Job No.
- B23LA05750
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** CONVERT DETACHED 20' X 24' REC ROOM TO ADU WITH ADDITION OF 7'3.25" X 21'7.5" AT THE REAR per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Current Status
- CofO Issued on 5/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | JESSE JIMENEZ |
| Corrections Issued | 4/5/2023 | JESSE JIMENEZ |
| Applicant returned to address corrections | 7/5/2023 | AUNG SOE |
| Applicant returned to address corrections | 7/20/2023 | MINA HABILI |
| Plan Check Approved | 7/26/2023 | EDWIN ESPIN |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 5/2/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
| CofO Issued | 5/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 5/1/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 5/16/2023 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | AHMED AMARRAGY |
| Construction near power lines | Cleared | 7/11/2023 | TINA MIRANDA |
Contact Information
| Architect | , ; Lic. No.: C34605 | 2129 LOELLA AVE VENICE, CA 90291 |
| Contractor | Ciccone Builders Inc; Lic. No.: 850466-B | , |
| Engineer | Vahabzadeh,, Reza; Lic. No.: S6538 | 13961 MOORPARK ST APT 207 SHERMAN OAKS, CA 91423 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2023 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Drilled-In Anchors | 11/29/2023 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/7/2023 | Conditional Approval | HERBERT GIRON |
| Special/Order Compliance | 12/7/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Rough | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/12/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/17/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 1/17/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 1/18/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 1/23/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/23/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 1/31/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 4/12/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 4/16/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 5/1/2024 | Approved | TEMISTOCLES CAAL |
| Final | 5/1/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 5/1/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 5/1/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 5/1/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 5/1/2024 | Approved | TEMISTOCLES CAAL |