40 E 18TH AVE 1-3 90291
Certificate Information: 40 E 18TH AVE 1-3 90291
- Application / Permit
- 23016-10000-09317
- Plan Check / Job No.
- B23LA05743
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- **ePlan** Attached Guestroom conversion to an Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | EDWIN ESPIN |
| Corrections Issued | 4/6/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 4/13/2023 | EDWIN ESPIN |
| Plan Check Approved | 9/14/2023 | EDWIN ESPIN |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 11/30/2023 | HERBERT GIRON |
| Permit Finaled | 12/5/2023 | DANIEL ORRANTE |
| CofO Issued | 12/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/11/2023 | ANTHONY MAINEZ |
| Tenant Habitability Plan | Cleared | 4/11/2023 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2023 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 4/21/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 4/21/2023 | SPENCER WEJROWSKI |
| Specific Plan | Cleared | 4/26/2023 | PEDRO AYALA |
| Specific Plan | Cleared | 4/26/2023 | PEDRO AYALA |
| Coastal Zone | Cleared | 7/19/2023 | JAZMIN ROQUE |
| Specific Plan | Cleared | 9/12/2023 | JACKSON OLSON |
Contact Information
| Architect | Jantzen,, Christof; Lic. No.: C29896 | 40 18TH AVENUE #1 VENICE, CA 90291 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/5/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 10/5/2023 | Approved | HERBERT GIRON |
| Final | 10/18/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/29/2023 | Approved | HERBERT GIRON |
| Final | 11/29/2023 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 11/29/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 11/29/2023 | Approved | HERBERT GIRON |