7511 N VINELAND AVE 91352

Certificate Information: 7511 N VINELAND AVE 91352

Application / Permit
23016-10000-08949
Plan Check / Job No.
B23VN03526
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT "UNIT B" PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/3/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 DANIEL YIP
Corrections Issued 3/28/2023 DANIEL YIP
Quality Review Completed 3/29/2023 GARO TELMI
Applicant returned to address corrections 6/22/2023 DANIEL YIP
Plan Check Approved 7/3/2023 DANIEL YIP
Issued 7/3/2023 APPLICANT
CofO in Progress 2/8/2024 JOHN COLEMAN
Permit Finaled 3/29/2024 RONALD MYRICK
CofO Issued 3/29/2024 RONALD MYRICK
Permit Finaled 3/29/2024 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/14/2023 NIKKI ZULUETA
Sewer availability Cleared 4/14/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/17/2023 NIKKI ZULUETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/19/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 7/20/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 7/20/2023 Partial Approval THOMAS FINNILA
Pre-Inspection 7/24/2023 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 7/26/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/11/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 8/31/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 8/31/2023 Not Ready for Inspection JOHN HAYES
Insulation 8/31/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/31/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/6/2023 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 9/6/2023 Not Ready for Inspection JACK KARGODORIAN
Pre-Inspection 9/6/2023 Not Ready for Inspection JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 9/6/2023 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 9/13/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/13/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/13/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/13/2023 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/21/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/21/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/21/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/21/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/27/2023 Approved JOHN HAYES
ELECTRICAL-Rough 9/27/2023 Approved JOHN HAYES
Green Building Rough 9/27/2023 Approved JOHN HAYES
HVAC-Rough 9/27/2023 Approved JOHN HAYES
PLUMBING-Rough 9/27/2023 Approved JOHN HAYES
Insulation 10/10/2023 Approved JOHN HAYES
Drywall Nailing 10/18/2023 Approved JOHN HAYES
Final 11/22/2023 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/22/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 11/22/2023 Approved CHRISTOPHER ROJAS
Final 12/4/2023 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready JOHN HAYES
Final 12/14/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Not Ready JENNIFER RABUCHIN
Final 1/31/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Not Ready CRAIG DAVIS
Final 2/8/2024 OK to Issue CofO JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Approved JOHN COLEMAN