6707 W 87TH PL 90045
Certificate Information: 6707 W 87TH PL 90045
- Application / Permit
- 23016-10000-08844
- Plan Check / Job No.
- B23LA05475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of an (E) 1-Story SFD, Remodel to Include Window and Door Replacement, Removal of Load Bearing Wall to be Replace by Beam, Kitchen and Additional Bath and Closet
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/7/2024
Permit Application Status History
| Submitted | 3/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | DAVID CASTILLO |
| Corrections Issued | 4/1/2023 | DAVID CASTILLO |
| Plan Check Approved | 7/27/2023 | JOE VO |
| Issued | 8/4/2023 | APPLICANT |
| Permit Finaled | 2/7/2024 | BOBBY KEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/4/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/4/2023 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/4/2023 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/10/2023 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 10/10/2023 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 10/18/2023 | No Access for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 11/7/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 11/7/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 11/7/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 11/7/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 11/7/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 11/9/2023 | Approved | BOBBY KEY |
| Insulation | 11/9/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 11/15/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/17/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/17/2024 | Approved | TEMISTOCLES CAAL |
| Final | 1/29/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 1/29/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Not Required | BOBBY KEY |
| Smoke Detectors | 1/29/2024 | Approved | BOBBY KEY |
| Final | 2/7/2024 | Permit Finaled | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Approved | BOBBY KEY |