640 N GARDNER ST 90036

Certificate Information: 640 N GARDNER ST 90036

Application / Permit
23016-10000-08828
Plan Check / Job No.
B23LA05464
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A NEW 20'-0" x 20'-0" ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 9/27/2023
Issuing Office
Current Status
CofO Issued on 6/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2023 APPLICANT
Assigned to Plan Check Engineer 4/11/2023 SARKIS HARABEDIAN
Corrections Issued 4/12/2023 SARKIS HARABEDIAN
Applicant returned to address corrections 8/15/2023 LUISANGEL VALENZUELA
Plan Check Approved 9/10/2023 LUISANGEL VALENZUELA
Issued 9/27/2023 APPLICANT
CofO in Progress 5/2/2024 AMIR NAZARIAN
Permit Finaled 6/3/2024 DEROLD HAUFF
CofO Issued 6/3/2024 DEROLD HAUFF
Permit Finaled 6/3/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 5/13/2023 CHRISTOPHER ROCHA
Address approval Cleared 7/8/2023 CHRISTOPHER ROCHA
Construction near power lines Cleared 8/11/2023 RIDWAN HARDY
Construction within easement Cleared 8/11/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/12/2023 CHRISTOPHER ROCHA

Contact Information

Contractor Gaga Builders Inc; Lic. No.: 1038675-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/16/2023 Partial Approval LILIANA PORTILLO
Underground Mechanical 10/16/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/19/2023 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 10/20/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/27/2023 Corrections Issued LILIANA PORTILLO
METHANE-Rough 11/27/2023 Approved LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 11/27/2023 Approved LILIANA PORTILLO
Underground Mechanical 11/27/2023 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 11/29/2023 Conditional Approval LILIANA PORTILLO
Deputy Wood Construction 1/5/2024 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 1/11/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved LILIANA PORTILLO
Insulation 1/18/2024 Approved LILIANA PORTILLO
Drywall Nailing 1/22/2024 Approved AMIR NAZARIAN
Shower Pan 1/22/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 1/24/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Not Ready AMIR NAZARIAN
Pre-Inspection 4/16/2024 Corrections Issued AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Not Ready ENRIQUE MIRELES
Final 5/1/2024 OK to Issue CofO AMIR NAZARIAN
Pre-Inspection 5/1/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Approved AMIR NAZARIAN
Smoke Detectors 5/1/2024 Approved AMIR NAZARIAN