640 N GARDNER ST 90036
Certificate Information: 640 N GARDNER ST 90036
- Application / Permit
- 23016-10000-08828
- Plan Check / Job No.
- B23LA05464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A NEW 20'-0" x 20'-0" ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 9/27/2023
- Issuing Office
- Current Status
- CofO Issued on 6/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2023 | SARKIS HARABEDIAN |
| Corrections Issued | 4/12/2023 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 8/15/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/10/2023 | LUISANGEL VALENZUELA |
| Issued | 9/27/2023 | APPLICANT |
| CofO in Progress | 5/2/2024 | AMIR NAZARIAN |
| Permit Finaled | 6/3/2024 | DEROLD HAUFF |
| CofO Issued | 6/3/2024 | DEROLD HAUFF |
| Permit Finaled | 6/3/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/13/2023 | CHRISTOPHER ROCHA |
| Address approval | Cleared | 7/8/2023 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 8/11/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/11/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Gaga Builders Inc; Lic. No.: 1038675-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2023 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 10/16/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 10/20/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | LILIANA PORTILLO |
| METHANE-Rough | 11/27/2023 | Approved | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 11/27/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/27/2023 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/29/2023 | Conditional Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 1/5/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/11/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | LILIANA PORTILLO |
| Insulation | 1/18/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/22/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 1/22/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 1/24/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Pre-Inspection | 4/16/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 5/1/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Pre-Inspection | 5/1/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 5/1/2024 | Approved | AMIR NAZARIAN |