585-585 1/2 W 16TH ST 90731

Certificate Information: 585-585 1/2 W 16TH ST 90731

Application / Permit
23016-10000-08826
Plan Check / Job No.
B23LA05454
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert Existing 187 SQ FT garage and 216 SQ FT portion of (E) SFD to be converted to new ADU per CA Govt. Code 65852.2(e)(1)(A). Construction per WFPP (ADDRESS OF EXISTING SFD IS 585 W 16TH ST AND NEW ATTACHED ADU ADDRESS IS 585 1/2 W 16TH ST)
Permit Issued
Issued on 6/12/2023
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 JASON JANGADA
Corrections Issued 4/1/2023 JASON JANGADA
Applicant returned to address corrections 5/12/2023 JASON JANGADA
Plan Check Approved 6/10/2023 ANDREW SANTIAGO
Issued 6/12/2023 APPLICANT
CofO in Progress 8/21/2023 JAMES CHAVEZ
CofO Issued 8/30/2023 ANSON MAGLASANG
Permit Finaled 8/30/2023 ANSON MAGLASANG

Permit Application Clearance Information

Tenant Habitability Plan Cleared 4/28/2023 ISMAEL HERNANDEZ
Address approval Cleared 5/11/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 5/11/2023 ANA SORIANO
Sewer availability Cleared 5/11/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2023 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 6/23/2023 Not Ready for Inspection ANSON MAGLASANG
Deputy Drilled-In Anchors 6/23/2023 Conditional Approval ANSON MAGLASANG
Green Building Rough 6/23/2023 Not Ready for Inspection ANSON MAGLASANG
Wood Frame 6/23/2023 Not Ready for Inspection ANSON MAGLASANG
Wood Frame 7/14/2023 Approved JAMES CHAVEZ
Insulation 7/17/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/17/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 7/28/2023 Partial Approval JAMES CHAVEZ
Final 7/28/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 7/28/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 7/28/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 7/28/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 8/7/2023 Approved JAMES CHAVEZ
Final 8/7/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 8/7/2023 Approved JAMES CHAVEZ
Smoke Detectors 8/7/2023 Approved JAMES CHAVEZ
Final 8/10/2023 OK to Issue CofO JAMES CHAVEZ