8022 S DUNBARTON AVE 90045

Certificate Information: 8022 S DUNBARTON AVE 90045

Application / Permit
23016-10000-08663
Plan Check / Job No.
B23LA05354
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A. WORK PER ENGINEERING.
Permit Issued
Issued on 8/10/2023
Issuing Office
Current Status
CofO Issued on 3/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 4/3/2023 ISIS ARGUETA
Corrections Issued 4/4/2023 ISIS ARGUETA
Applicant returned to address corrections 7/19/2023 ISIS ARGUETA
Plan Check Approved 8/1/2023 ISIS ARGUETA
Issued 8/10/2023 APPLICANT
CofO in Progress 3/11/2024 BOBBY KEY
Permit Finaled 3/15/2024 DANIEL ORRANTE
CofO Issued 3/15/2024 DANIEL ORRANTE
Permit Finaled 3/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/4/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 4/4/2023 DARIN LAM
Sewer availability Cleared 4/4/2023 DARIN LAM
Specific Plan Cleared 4/25/2023 ROBERT SANCHEZ
Construction near power lines Cleared 7/28/2023 TINA MIRANDA

Contact Information

Contractor Manchen Construction Inc ; Lic. No.: 1043435-B       ,
Contractor Manchen Construction Inc; Lic. No.: 1043435-B       ,
Engineer Boranian,, Paul; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/23/2023 Corrections Issued BOBBY KEY
Underground Mechanical 8/23/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 8/31/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 9/15/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 10/12/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 10/12/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Approved BOBBY KEY
Footing/Foundation/Slab 10/12/2023 Approved BOBBY KEY
PLUMBING-Rough 10/12/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 10/24/2023 Approved BOBBY KEY
Pre-Inspection 10/24/2023 Partial Inspection BOBBY KEY
BUILDING-Rough-Frame 11/6/2023 Approved BOBBY KEY
Green Building Rough 11/6/2023 Approved BOBBY KEY
Interior/Exterior Lathing 11/6/2023 Partial Approval BOBBY KEY
Insulation 11/9/2023 Approved BOBBY KEY
Drywall Nailing 11/17/2023 Approved TEMISTOCLES CAAL
Shower Pan 11/21/2023 Approved BOBBY KEY
Interior/Exterior Lathing 12/1/2023 Approved BOBBY KEY
ELECTRICAL-Final 2/27/2024 Corrections Issued BOBBY KEY
Final 2/27/2024 Corrections Issued BOBBY KEY
Green Building Final 2/27/2024 Approved BOBBY KEY
HVAC-Final 2/27/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 2/27/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 2/27/2024 Approved BOBBY KEY
ELECTRICAL-Final 3/11/2024 Approved BOBBY KEY
Final 3/11/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 3/11/2024 Approved BOBBY KEY