16828 W RINALDI ST 91344
Certificate Information: 16828 W RINALDI ST 91344
- Application / Permit
- 23016-10000-08611
- Plan Check / Job No.
- B23LA05313
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING (E) GARAGE AND (E)STORAGE TO A NEW ACCESSORY DWELLING UNIT ( ADU) PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | ZAW HAN |
| Corrections Issued | 4/3/2023 | ZAW HAN |
| Applicant returned to address corrections | 4/6/2023 | VICTOR CHEN |
| Building Plans Picked Up | 4/6/2023 | APPLICANT |
| Plan Check Approved | 4/24/2023 | SHANGQIN XIE |
| Issued | 4/27/2023 | APPLICANT |
| CofO in Progress | 10/6/2023 | JAVIER RAMOS JR |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/6/2023 | OSCAR CASTRO |
| Address approval | Cleared | 4/13/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 4/13/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | FERNANDO GIL |
| Grading Pre-Inspection | Cleared | 4/21/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/1/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/25/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 5/25/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 5/25/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/21/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/21/2023 | Approved | JAVIER RAMOS JR |
| Wood Frame | 6/21/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/5/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 7/5/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/5/2023 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 7/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/5/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/11/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/11/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/11/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 7/11/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/25/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/25/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 7/25/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/28/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 8/4/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | JAVIER RAMOS JR |
| Final | 9/25/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 9/25/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 9/25/2023 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 9/25/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 9/25/2023 | Approved | JAVIER RAMOS JR |
| Final | 9/29/2023 | Partial Approval | ROBERT GOLD |
| Final | 10/5/2023 | OK to Issue CofO | JAVIER RAMOS JR |