1121 W 20TH ST 90731

Certificate Information: 1121 W 20TH ST 90731

Application / Permit
23016-10000-08537
Plan Check / Job No.
B23LA05270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE 339SF INTO ADU PER WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A))
Permit Issued
Issued on 10/24/2023
Issuing Office
San Pedro
Current Status
Issued on 10/24/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 AUNG SOE
Corrections Issued 4/3/2023 AUNG SOE
Building Plans Picked Up 4/4/2023 APPLICANT
Plan Check Approved 9/29/2023 ADAM HEGAZI
Issued 10/24/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/12/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 4/12/2023 KHAING AYE
Sewer availability Cleared 4/12/2023 KHAING AYE
Grading Pre-Inspection Cleared 4/17/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2025 Approved JOSEPH MCGARRY
Pre-Inspection 9/24/2025 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 9/29/2025 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 10/1/2025 Partial Inspection JOSEPH MCGARRY
Deputy Drilled-In Anchors 10/6/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/6/2025 Approved BEN MOLSTAD
Wood Frame 10/17/2025 Partial Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 3/9/2026 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 3/9/2026 Partial Inspection JOSEPH MCGARRY
Green Building Rough 3/9/2026 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/9/2026 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 3/17/2026 Partial Approval JOSEPH MCGARRY
Green Building Rough 3/17/2026 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 3/17/2026 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/31/2026 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/31/2026 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 3/31/2026 Approved JOSEPH MCGARRY
PLUMBING-Rough 3/31/2026 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/15/2026 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 4/15/2026 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 5/26/2026 Approved JOSEPH MCGARRY