4917 N AVOCA ST 90041

Certificate Information: 4917 N AVOCA ST 90041

Application / Permit
23016-10000-08176
Plan Check / Job No.
B23LA05064
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to ADU per state law. Scope of work to include reframing the existing roof to increase the building height. All work per engineered design.
Permit Issued
Issued on 5/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/28/2023 CAROLEAN BASMA
Corrections Issued 3/30/2023 CAROLEAN BASMA
Building Plans Picked Up 4/4/2023 APPLICANT
Applicant returned to address corrections 5/9/2023 GEORGE ALVAREZ
Plan Check Approved 5/11/2023 DANIEL SMILEY
Issued 5/23/2023 APPLICANT
CofO in Progress 1/25/2024 CRAIG VAUGHAN
CofO in Progress 1/25/2024 CRAIG VAUGHAN
Permit Finaled 1/27/2024 DEROLD HAUFF
CofO Issued 1/27/2024 DEROLD HAUFF
Permit Finaled 1/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/27/2023 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 4/27/2023 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 4/27/2023 CHRISTOPHER ROCHA
Sewer availability Cleared 4/27/2023 CHRISTOPHER ROCHA
Grading Pre-Inspection Cleared 5/9/2023 ALEXANDER HELFER

Contact Information

Contractor Collins Construction Company; Lic. No.: 520023-B 3248 WAVERLY DRIVE      LOS ANGELES, CA 90027
Engineer Ficinski,, Marek; Lic. No.: S3534 4850 N LANTE ST      BALDWIN PARK, CA 91706

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 8/22/2023 Partial Approval CRAIG VAUGHAN
Wood Frame 8/22/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/12/2023 Corrections Issued ROY SPAULDING
HVAC-Rough 9/12/2023 Corrections Issued ROY SPAULDING
PLUMBING-Rough 9/12/2023 Approved ROY SPAULDING
Drywall Nailing 9/19/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 9/22/2023 Approved CRAIG VAUGHAN
Wood Frame 9/22/2023 Approved CRAIG VAUGHAN
Drywall Nailing 10/10/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/10/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/24/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/24/2023 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 10/24/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/27/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 1/4/2024 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/4/2024 Approved CRAIG VAUGHAN
Final 1/4/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/4/2024 Approved CRAIG VAUGHAN
Green Building Rough 1/4/2024 Approved CRAIG VAUGHAN
HVAC-Final 1/4/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 1/4/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/4/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 1/4/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 1/12/2024 OK to Issue CofO CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/12/2024 Approved CRAIG VAUGHAN