11314 W DELANO ST 91606
Certificate Information: 11314 W DELANO ST 91606
- Application / Permit
- 23016-10000-08169
- Plan Check / Job No.
- B23LA05061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- KITCHEN REMODEL WITH REMOVAL OF BEARING WALL
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/4/2023
Permit Application Status History
| Submitted | 3/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2023 | ZAW HAN |
| Corrections Issued | 3/21/2023 | ZAW HAN |
| Plan Check Approved | 3/23/2023 | MINA HABILI |
| Issued | 3/23/2023 | APPLICANT |
| Permit Finaled | 8/3/2023 | JUAN VALENZUELA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Cavalier Builders Inc; Lic. No.: 758563-B | 6520 PLATT AVE #732 WEST HILLS, CA 91307 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/8/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 5/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 5/8/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/2/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/2/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 6/2/2023 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/2/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | ROBERT GOLD |
| ELECTRICAL-Rough | 6/8/2023 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 6/8/2023 | Approved | ROBERT GOLD |
| Drywall Nailing | 6/13/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 6/13/2023 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Final | 8/1/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 8/1/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 8/1/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 8/1/2023 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 8/1/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/3/2023 | Approved | JUAN VALENZUELA |
| Final | 8/3/2023 | Permit Finaled | JUAN VALENZUELA |
| HVAC-Final | 8/3/2023 | Approved | JUAN VALENZUELA |