652 1/2 E SUNSET AVE 90291
Certificate Information: 652 1/2 E SUNSET AVE 90291
- Application / Permit
- 23016-10000-08157
- Plan Check / Job No.
- B23LA05049
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert Existing Detached Garage to ADU WITH ADDITION PER LAMC 12.22 A.33 (c)(d) *****COMPLY WITH DEPARTMENT ORDER****
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Current Status
- Issued on 1/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | KHUONG TRUONG |
| Corrections Issued | 3/30/2023 | KHUONG TRUONG |
| Plan Check Approved | 1/18/2024 | KHUONG TRUONG |
| Issued | 1/19/2024 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/3/2023 | ALESSANDRO MERCURI |
| Address approval | Cleared | 4/5/2023 | DARIN LAM |
| Miscellaneous | Cleared | 4/5/2023 | RYAN LY |
| Roof/Waste drainage to street | Cleared | 4/5/2023 | DARIN LAM |
| ZI | Cleared | 4/5/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2023 | DARIN LAM |
| Sewer availability | Cleared | 4/10/2023 | DARIN LAM |
| Coastal Zone | Cleared | 1/15/2024 | RYAN LY |
| Coastal Zone | Cleared | 1/15/2024 | RYAN LY |
| Specific Plan | Cleared | 1/15/2024 | RYAN LY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2024 | Not Ready for Inspection | RYAN BARNES |
| Pre-Inspection | 2/8/2024 | Partial Approval | RYAN BARNES |
| Footing/Foundation/Slab | 2/21/2024 | Approved | RYAN BARNES |
| Wood Frame | 2/21/2024 | Partial Approval | RYAN BARNES |
| Insulation | 2/26/2024 | Partial Approval | RYAN BARNES |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 2/27/2024 | Approved | RYAN BARNES |
| Green Building Rough | 2/27/2024 | Approved | RYAN BARNES |
| Insulation | 2/27/2024 | Approved | RYAN BARNES |
| Drywall Nailing | 2/29/2024 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 2/29/2024 | Approved | RYAN BARNES |
| Final | 3/13/2024 | Not Ready for Inspection | RYAN BARNES |
| Green Building Final | 3/13/2024 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 3/13/2024 | Approved | RYAN BARNES |
| Final | 3/15/2024 | Conditional Approval | RYAN BARNES |