564 W 149TH ST 90248

Certificate Information: 564 W 149TH ST 90248

Application / Permit
23016-10000-08102
Plan Check / Job No.
B23LA05023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to ADU per State Law, CA Govt. Code 65852.2(e)(1)(A), per WFPP
Permit Issued
Issued on 9/1/2023
Issuing Office
Current Status
Issued on 9/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/29/2023 MINA HABILI
Corrections Issued 3/29/2023 MINA HABILI
Plan Check Approved 7/29/2023 JOE VO
Issued 9/1/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/11/2023 ANA SORIANO
Sewer availability Cleared 7/11/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 7/17/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/2/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 4/8/2024 Not Ready for Inspection JAMES CHAVEZ
Deputy Drilled-In Anchors 4/25/2024 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 5/3/2024 Corrections Issued JAMES CHAVEZ
Special/Order Compliance 5/3/2024 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 5/6/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/6/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 7/17/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 7/22/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 10/17/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 10/17/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 11/25/2024 Approved BEN MOLSTAD
HVAC-Rough 11/27/2024 Approved BEN MOLSTAD
PLUMBING-Rough 11/27/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 12/12/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Rough 12/12/2024 Approved BEN MOLSTAD
Deputy Wood Construction 12/19/2024 Conditional Approval BEN MOLSTAD
Insulation 2/21/2025 Corrections Issued BEN MOLSTAD
Insulation 3/7/2025 Approved BEN MOLSTAD
Deputy Wood Construction 6/26/2025 Conditional Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved JOSEPH MCGARRY
Drywall Nailing 9/3/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/3/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Final 11/6/2025 Corrections Issued BEN MOLSTAD
Sewer 11/12/2025 Approved BEN MOLSTAD
PLUMBING-Final 11/14/2025 No Access for Inspection BEN MOLSTAD
Shower Pan 11/17/2025 Corrections Issued BEN MOLSTAD
Shower Pan 12/10/2025 Corrections Issued BEN MOLSTAD
Shower Pan 12/23/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/13/2026 Approved BEN MOLSTAD
BUILDING-Rough-Frame 4/24/2026 Approved BEN MOLSTAD
Final 4/24/2026 Corrections Issued BEN MOLSTAD
Green Building Final 4/24/2026 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 4/24/2026 Approved BEN MOLSTAD
HVAC-Final 4/24/2026 Corrections Issued BEN MOLSTAD
METHANE-Final 4/24/2026 Approved BEN MOLSTAD
METHANE-Rough 4/24/2026 Approved BEN MOLSTAD
PLUMBING-Final 4/24/2026 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Approved BEN MOLSTAD
Smoke Detectors 4/24/2026 Not Ready for Inspection BEN MOLSTAD