130 S MYERS ST 90033

Certificate Information: 130 S MYERS ST 90033

Application / Permit
23016-10000-08093
Plan Check / Job No.
B23LA05018
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
*eplan* Tenant improvement at existing Warehouse/Office. To include new exterior openings, new floor openings at existing Mezzanine, new non load-bearing partitions, & restrooms.
Permit Issued
Issued on 8/11/2023
Issuing Office
Current Status
Permit Finaled on 6/27/2025

Permit Application Status History

Submitted 3/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 PRANITA SHAH
Corrections Issued 4/11/2023 PRANITA SHAH
Quality Review Completed 4/13/2023 GARO TELMI
Applicant returned to address corrections 7/13/2023 PRANITA SHAH
Applicant returned to address corrections 7/25/2023 PRANITA SHAH
Plan Check Approved 8/9/2023 PRANITA SHAH
Issued 8/11/2023 APPLICANT
Permit Finaled 6/27/2025 RONALD JIMENEZ

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 4/19/2023 MAX LODER
Historic monument Cleared 4/19/2023 MAX LODER
Clean Up Green Up Cleared 4/21/2023 RYAN LY
ZI Cleared 4/21/2023 RYAN LY
Redevelopment Project Area Cleared 4/26/2023 SUSAN WONG
Green Code Cleared 6/27/2023 KHEDER ALRAZAA
DAS Clearance Cleared 6/29/2023 Shangqin Xie

Contact Information

Architect Fleming,, Cynthia Marie; Lic. No.: C17066 24361 SANTA CLARA AVENUE      DANA POINT, CA 92629
Contractor Arco / Murray National Norcal Llc; Lic. No.: 1070665-B       ,
Engineer Thompson,, Douglas Sevier; Lic. No.: S2578 21084 BAKE PARKWAY SUITE 100      LAKE FOREST, CA 92630

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 9/22/2023 Partial Inspection JULIAN CAPUCETTI
Deputy Drilled-In Anchors 9/27/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Drilled-In Anchors 9/28/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Concrete 9/28/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Masonry 9/28/2023 Conditional Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 9/28/2023 Not Ready for Inspection JULIAN CAPUCETTI
Masonry Wall/Backfill 9/28/2023 Not Ready for Inspection JULIAN CAPUCETTI
Deputy Drilled-In Anchors 9/29/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Concrete 9/29/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Reinf. Masonry 9/29/2023 Conditional Approval JULIAN CAPUCETTI
Deputy Steel/Welding 10/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 10/16/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Steel/Welding 10/17/2023 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 10/18/2023 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 10/19/2023 Conditional Approval RAFAEL CORTES
Deputy Drilled-In Anchors 10/20/2023 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 10/20/2023 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 10/24/2023 Conditional Approval JACOB MYERS
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/30/2023 Partial Approval RICARDO ROBLES
Deputy Reinf. Concrete 10/31/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 11/13/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 11/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/17/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Steel/Welding 11/17/2023 Conditional Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 11/17/2023 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 11/17/2023 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 11/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 11/22/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/22/2023 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/28/2023 Conditional Approval ALFREDO LOPEZ
Deputy Steel/Welding 11/28/2023 Conditional Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 11/28/2023 Not Ready for Inspection ALFREDO LOPEZ
Deputy Drilled-In Anchors 11/29/2023 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 11/29/2023 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 11/29/2023 Approved RAFAEL CORTES
Deputy Drilled-In Anchors 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 11/30/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/5/2023 Partial Approval JEROME BLACKWOOD
Deputy Steel/Welding 12/5/2023 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 12/5/2023 Corrections Issued JEROME BLACKWOOD
Deputy Reinf. Concrete 12/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/7/2023 Conditional Approval RICARDO ROBLES
Deputy Steel/Welding 12/7/2023 Conditional Approval RICARDO ROBLES
Excavation/Setback/Form/Re-Bar 12/7/2023 Corrections Issued RICARDO ROBLES
Deputy Reinf. Concrete 12/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 12/11/2023 Conditional Approval RAMAZANALI ALMASI
Insulation 12/11/2023 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 12/11/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 12/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 12/12/2023 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 12/13/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 12/13/2023 Partial Approval RAMAZANALI ALMASI
Structural Steel Frame 12/13/2023 Partial Inspection RAMAZANALI ALMASI
Deputy Reinf. Concrete 12/14/2023 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 12/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 12/22/2023 Conditional Approval RAMAZANALI ALMASI
Light Gage Steel Frame 12/22/2023 Partial Approval RAMAZANALI ALMASI
Structural Steel Frame 12/22/2023 Corrections Issued RAMAZANALI ALMASI
Deputy Drilled-In Anchors 1/3/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 1/3/2024 Conditional Approval MICHAEL ROSENBERG
Light Gage Steel Frame 1/5/2024 Partial Approval RAMAZANALI ALMASI
Structural Steel Frame 1/5/2024 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 1/11/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 1/16/2024 Partial Approval RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 1/16/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 1/16/2024 Not Ready for Inspection RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 1/18/2024 Partial Approval RAMAZANALI ALMASI
Structural Steel Frame 1/18/2024 Approved RAMAZANALI ALMASI
Wood Frame 1/18/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 1/19/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 1/19/2024 Partial Inspection RAMAZANALI ALMASI
Drywall Nailing 1/22/2024 Partial Approval RICARDO ROBLES
Insulation 1/22/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 1/22/2024 Partial Approval RICARDO ROBLES
Wood Frame 1/22/2024 Partial Approval RICARDO ROBLES
Insulation 1/24/2024 Approved JACOB MYERS
Light Gage Steel Frame 1/24/2024 Partial Approval JACOB MYERS
Wood Frame 1/24/2024 Partial Approval JACOB MYERS
Drywall Nailing 1/29/2024 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 1/30/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 2/2/2024 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 2/2/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/2/2024 Partial Approval RAMAZANALI ALMASI
Interior/Exterior Lathing 2/6/2024 Not Ready for Inspection DARRYL ARNOLD
Light Gage Steel Frame 2/6/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 2/6/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 2/7/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/7/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 2/7/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 2/8/2024 Approved RAMAZANALI ALMASI
Insulation 2/9/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/9/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 2/12/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 2/13/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 2/16/2024 Partial Approval RAMAZANALI ALMASI
Insulation 2/16/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/16/2024 Partial Approval RAMAZANALI ALMASI
T-Bar Ceiling 2/16/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 2/21/2024 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 2/21/2024 Not Ready for Inspection RAMAZANALI ALMASI
Drywall Nailing 2/23/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/23/2024 Not Ready for Inspection RAMAZANALI ALMASI
Pre-Inspection 2/23/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 3/4/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 3/4/2024 Not Ready for Inspection RAMAZANALI ALMASI
Light Gage Steel Frame 3/5/2024 Partial Approval RONALD JIMENEZ
Pre-Inspection 3/5/2024 Approved RONALD JIMENEZ
T-Bar Ceiling 3/5/2024 Not Ready for Inspection RONALD JIMENEZ
Drywall Nailing 3/12/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 3/12/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 3/14/2024 Partial Approval RONALD JIMENEZ
Insulation 3/14/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 3/14/2024 Partial Approval RONALD JIMENEZ
Wood Frame 3/14/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 3/15/2024 Partial Approval RONALD JIMENEZ
Insulation 3/15/2024 Partial Approval RONALD JIMENEZ
Wood Frame 3/15/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 3/18/2024 Partial Approval RONALD JIMENEZ
Wood Frame 3/18/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 3/20/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 3/20/2024 Not Ready for Inspection RONALD JIMENEZ
Drywall Nailing 3/27/2024 Conditional Approval RONALD JIMENEZ
Light Gage Steel Frame 3/27/2024 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 3/27/2024 Partial Approval RONALD JIMENEZ
Wood Frame 4/1/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/3/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 4/3/2024 Partial Approval RONALD JIMENEZ
Wood Frame 4/3/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 4/4/2024 Approved RAMAZANALI ALMASI
Drywall Nailing 4/8/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 4/8/2024 Approved RONALD JIMENEZ
Drywall Nailing 4/10/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/16/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 5/16/2024 Approved RONALD JIMENEZ
Pre-Inspection 5/16/2024 Approved RONALD JIMENEZ
Special/Order Compliance 6/11/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 6/12/2024 Partial Inspection RONALD JIMENEZ
Pre-Inspection 5/13/2025 Corrections Issued RONALD JIMENEZ
Final 5/14/2025 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 5/14/2025 Approved RONALD JIMENEZ
Pre-Inspection 5/14/2025 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 5/14/2025 Approved RONALD JIMENEZ
Final 6/18/2025 Conditional Approval RONALD JIMENEZ
Final 6/27/2025 Permit Finaled RONALD JIMENEZ