Masonry Wall/Backfill
|
9/22/2023
|
Partial Inspection
|
JULIAN CAPUCETTI
|
|
Deputy Drilled-In Anchors
|
9/27/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Drilled-In Anchors
|
9/28/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Reinf. Concrete
|
9/28/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Reinf. Masonry
|
9/28/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Footing/Foundation/Slab
|
9/28/2023
|
Not Ready for Inspection
|
JULIAN CAPUCETTI
|
|
Masonry Wall/Backfill
|
9/28/2023
|
Not Ready for Inspection
|
JULIAN CAPUCETTI
|
|
Deputy Drilled-In Anchors
|
9/29/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Reinf. Concrete
|
9/29/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Reinf. Masonry
|
9/29/2023
|
Conditional Approval
|
JULIAN CAPUCETTI
|
|
Deputy Steel/Welding
|
10/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
10/16/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
10/17/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
10/18/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
10/19/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Drilled-In Anchors
|
10/20/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
10/20/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
10/23/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
10/24/2023
|
Conditional Approval
|
JACOB MYERS
|
|
Deputy Drilled-In Anchors
|
10/25/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
10/30/2023
|
Partial Approval
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
10/31/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
11/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
11/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
11/17/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Deputy Steel/Welding
|
11/17/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Excavation/Setback/Form/Re-Bar
|
11/17/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Footing/Foundation/Slab
|
11/17/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Deputy Drilled-In Anchors
|
11/22/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
11/22/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Footing/Foundation/Slab
|
11/22/2023
|
Partial Approval
|
KATY RAMIREZ
|
|
Deputy Drilled-In Anchors
|
11/28/2023
|
Conditional Approval
|
ALFREDO LOPEZ
|
|
Deputy Steel/Welding
|
11/28/2023
|
Conditional Approval
|
ALFREDO LOPEZ
|
|
Excavation/Setback/Form/Re-Bar
|
11/28/2023
|
Not Ready for Inspection
|
ALFREDO LOPEZ
|
|
Deputy Drilled-In Anchors
|
11/29/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Deputy Steel/Welding
|
11/29/2023
|
Conditional Approval
|
RAFAEL CORTES
|
|
Excavation/Setback/Form/Re-Bar
|
11/29/2023
|
Approved
|
RAFAEL CORTES
|
|
Deputy Drilled-In Anchors
|
11/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
11/30/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/5/2023
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Deputy Steel/Welding
|
12/5/2023
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Excavation/Setback/Form/Re-Bar
|
12/5/2023
|
Corrections Issued
|
JEROME BLACKWOOD
|
|
Deputy Reinf. Concrete
|
12/6/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
12/6/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
12/7/2023
|
Conditional Approval
|
RICARDO ROBLES
|
|
Deputy Steel/Welding
|
12/7/2023
|
Conditional Approval
|
RICARDO ROBLES
|
|
Excavation/Setback/Form/Re-Bar
|
12/7/2023
|
Corrections Issued
|
RICARDO ROBLES
|
|
Deputy Reinf. Concrete
|
12/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
12/8/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
12/11/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Insulation
|
12/11/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
12/11/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
12/12/2023
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Insulation
|
12/12/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
12/13/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Excavation/Setback/Form/Re-Bar
|
12/13/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
12/13/2023
|
Partial Inspection
|
RAMAZANALI ALMASI
|
|
Deputy Reinf. Concrete
|
12/14/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Deputy Drilled-In Anchors
|
12/21/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
12/22/2023
|
Conditional Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
12/22/2023
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
12/22/2023
|
Corrections Issued
|
RAMAZANALI ALMASI
|
|
Deputy Drilled-In Anchors
|
1/3/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
1/3/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Light Gage Steel Frame
|
1/5/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
1/5/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Insulation
|
1/11/2024
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
1/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
1/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
1/16/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/18/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
1/18/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Structural Steel Frame
|
1/18/2024
|
Approved
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
1/18/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
1/19/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
1/19/2024
|
Partial Inspection
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
1/22/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
1/22/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Light Gage Steel Frame
|
1/22/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Wood Frame
|
1/22/2024
|
Partial Approval
|
RICARDO ROBLES
|
|
Insulation
|
1/24/2024
|
Approved
|
JACOB MYERS
|
|
Light Gage Steel Frame
|
1/24/2024
|
Partial Approval
|
JACOB MYERS
|
|
Wood Frame
|
1/24/2024
|
Partial Approval
|
JACOB MYERS
|
|
Drywall Nailing
|
1/29/2024
|
Partial Approval
|
KATY RAMIREZ
|
|
Interior/Exterior Lathing
|
1/30/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
|
Drywall Nailing
|
2/2/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Insulation
|
2/2/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/2/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Interior/Exterior Lathing
|
2/6/2024
|
Not Ready for Inspection
|
DARRYL ARNOLD
|
|
Light Gage Steel Frame
|
2/6/2024
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Wood Frame
|
2/6/2024
|
Conditional Approval
|
DARRYL ARNOLD
|
|
Drywall Nailing
|
2/7/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/7/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
2/7/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Wood Frame
|
2/8/2024
|
Approved
|
RAMAZANALI ALMASI
|
|
Insulation
|
2/9/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/9/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
2/12/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
2/13/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
2/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Insulation
|
2/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
T-Bar Ceiling
|
2/16/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
2/21/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/21/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
2/23/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
2/23/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Pre-Inspection
|
2/23/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
3/4/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
3/4/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
3/5/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Pre-Inspection
|
3/5/2024
|
Approved
|
RONALD JIMENEZ
|
|
T-Bar Ceiling
|
3/5/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/12/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Light Gage Steel Frame
|
3/12/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
3/14/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
3/14/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
3/14/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
3/14/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/15/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Insulation
|
3/15/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
3/15/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/18/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
3/18/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/20/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
3/20/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
3/27/2024
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
3/27/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Wood Frame
|
3/27/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
4/1/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/3/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/3/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Wood Frame
|
4/3/2024
|
Approved
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
4/4/2024
|
Approved
|
RAMAZANALI ALMASI
|
|
Drywall Nailing
|
4/8/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Interior/Exterior Lathing
|
4/8/2024
|
Approved
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/10/2024
|
Partial Approval
|
RONALD JIMENEZ
|
|
Drywall Nailing
|
4/16/2024
|
Approved
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
5/16/2024
|
Approved
|
RONALD JIMENEZ
|
|
Pre-Inspection
|
5/16/2024
|
Approved
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
6/11/2024
|
Approved
|
RONALD JIMENEZ
|
|
Light Gage Steel Frame
|
6/12/2024
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Pre-Inspection
|
5/13/2025
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Final
|
5/14/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
Green Building Final
|
5/14/2025
|
Approved
|
RONALD JIMENEZ
|
|
Pre-Inspection
|
5/14/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
5/14/2025
|
SGSOV Approved
|
RONALD JIMENEZ
|
|
Smoke Detectors
|
5/14/2025
|
Approved
|
RONALD JIMENEZ
|
|
Final
|
6/18/2025
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Final
|
6/27/2025
|
Permit Finaled
|
RONALD JIMENEZ
|