2809 S OAKHURST AVE 90034
Certificate Information: 2809 S OAKHURST AVE 90034
- Application / Permit
- 23016-10000-08049
- Plan Check / Job No.
- B23LA04217
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION INTO DETACHED ADU (PER CA GOVT. CODE 65852.2( e)(1)(A);
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/20/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 4/7/2023 | FARUK SEZER |
| Applicant returned to address corrections | 6/5/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/23/2023 | CRYSTEL MAALOUF |
| Issued | 6/23/2023 | APPLICANT |
| Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
| CofO Issued | 8/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2023 | DARIN LAM |
| Sewer availability | Cleared | 4/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | DARIN LAM |
| Construction near power lines | Cleared | 6/10/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 6/23/2023 | CRYSTEL MAALOUF |
Contact Information
| Architect | Ribeiro, De Moura, Ricardo Jorge; Lic. No.: C38075 | 5236 YARMOUTH AVE #113 ENCINO, CA 91316 |
| Contractor | Owner-Builder | , |
| Engineer | Ostowari,, Sohrab; Lic. No.: C41014 | 7012 HELMSDALE RD WEST HILLS, CA 91307 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/11/2023 | Partial Approval | CLAYTON GRAHAM |
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 11/20/2023 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/21/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 12/13/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/21/2023 | Corrections Issued | BEN MOLSTAD |
| Insulation | 12/26/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/2/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/8/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/11/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 6/5/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 6/6/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/6/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/17/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 6/17/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Gas Test | 6/21/2024 | Approved | SEAN HAUPT |
| HVAC-Final | 6/21/2024 | Approved | SEAN HAUPT |
| PLUMBING-Final | 6/21/2024 | Approved | SEAN HAUPT |
| Pool/Spa Cover | 6/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| Final | 6/26/2024 | Corrections Issued | SEAN HAUPT |
| METHANE-Final | 6/26/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/26/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 6/26/2024 | Approved | SEAN HAUPT |
| Final | 8/5/2024 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 8/5/2024 | Approved | ASHLEY THOMPSON |