1762 1/2 E 111TH PL 90059

Certificate Information: 1762 1/2 E 111TH PL 90059

Application / Permit
23016-10000-07988
Plan Check / Job No.
B23LA04961
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) 15'-6' X 26'-6" GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(A) NFPA-13D FIRE SPRINKLERED THROUGHOUT ***COMPLY WITH DEPARTMENT ORDER effective date 12/20/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE *Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
Permit Issued
Issued on 12/11/2024
Issuing Office
Current Status
CofO Issued on 4/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 DANIEL ABRAMYAN
Corrections Issued 4/2/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 9/18/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/16/2024 KAMYAR EMAMI
Plan Check Approved 11/13/2024 KAMYAR EMAMI
Issued 12/11/2024 APPLICANT
CofO in Progress 9/30/2025 BRIAN CHRISTIAN
Permit Finaled 4/14/2026 CLAUDIO MORENO
CofO Issued 4/14/2026 CLAUDIO MORENO
Permit Finaled 4/14/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 4/4/2024 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 4/4/2024 JILVER MAZARIEGOS
Sewer availability Cleared 4/4/2024 JILVER MAZARIEGOS
Roof/Waste drainage to street Cleared 10/17/2024 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2025 Approved KEITH EDGHILL
Footing/Foundation/Slab 4/8/2025 Approved KEITH EDGHILL
ELECTRICAL-Rough 5/2/2025 Approved KEITH EDGHILL
PLUMBING-Rough 5/2/2025 Not Ready for Inspection KEITH EDGHILL
PLUMBING-Rough 5/7/2025 Approved KEITH EDGHILL
PLUMBING-Rough 5/15/2025 Approved KEITH EDGHILL
Shower Pan 5/20/2025 Approved KEITH EDGHILL
Drywall Nailing 5/30/2025 Approved KEITH EDGHILL
Green Building Rough 5/30/2025 Approved KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Corrections Issued KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 8/15/2025 Corrections Issued KEITH EDGHILL
BUILDING-Rough-Frame 9/18/2025 Approved KEITH EDGHILL
ELECTRICAL-Final 9/18/2025 Corrections Issued KEITH EDGHILL
Final 9/18/2025 Corrections Issued KEITH EDGHILL
Green Building Final 9/18/2025 Approved KEITH EDGHILL
HVAC-Final 9/18/2025 Approved KEITH EDGHILL
PLUMBING-Final 9/18/2025 Approved KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready KEITH EDGHILL
Smoke Detectors 9/18/2025 Approved KEITH EDGHILL
ELECTRICAL-Final 9/23/2025 Corrections Issued KEITH EDGHILL
Final 9/25/2025 OK to Issue CofO KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Approved KEITH EDGHILL