430 E 108TH ST 90061
Certificate Information: 430 E 108TH ST 90061
- Application / Permit
- 23016-10000-07823
- Plan Check / Job No.
- B23LA04848
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF (E) 1-STORY FRONT SFD TO ADD BATHROOM AND LAUNDRY ROOM, RESTORE AND REMODEL (E) SFD DUE TO FIRE AND WATER DAMAGE. INSTALL INSULATION AND REPLACE ALL WINDOWS **SFD TO BE FULLY SPRINKLERED BY NFPA-13D** SEE COMMENT
- Permit Issued
- Issued on 7/14/2023
- Issuing Office
- Metro
- Current Status
- Issued on 7/14/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2023 | WEIJIAN HUANG |
| Corrections Issued | 3/17/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 3/30/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 4/24/2023 | MINA HABILI |
| Plan Check Approved | 5/25/2023 | YAQUB MIRZA |
| Issued | 7/14/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | JEANIE LAM |
Contact Information
| Contractor | N 2 U Construction; Lic. No.: 930365-B | P O BOX 82446 LOS ANGELES, CA 90082 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/22/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 10/13/2023 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 10/23/2023 | Partial Approval | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2024 | Corrections Issued | JAMES CHAVEZ |
| Wood Frame | 2/6/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 3/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 3/12/2024 | Partial Inspection | BEN MOLSTAD |
| Wood Frame | 5/2/2024 | Corrections Issued | BEN MOLSTAD |
| Underground Mechanical | 12/27/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 7/1/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/1/2025 | Approved | JOHN KLARIN |
| Drywall Nailing | 9/19/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 9/19/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 10/2/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 10/2/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 10/2/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | ANTHONY EGSON |
| Sewer | 10/2/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/7/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/19/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 2/9/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 2/9/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 2/9/2026 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 3/25/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 3/25/2026 | Approved | ARTHUR NEGRETE |