3661 N LONGVIEW VALLEY ROAD 91423

Certificate Information: 3661 N LONGVIEW VALLEY ROAD 91423

Application / Permit
23016-10000-07379
Plan Check / Job No.
B23LA04516
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Interior/exterior Remodel to (E) Single Family Dwelling w/ attached carport
Permit Issued
Issued on 8/7/2023
Issuing Office
Current Status
Permit Finaled on 2/22/2024

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 ALFREDO JARA
Corrections Issued 3/20/2023 ALFREDO JARA
Applicant returned to address corrections 4/12/2023 ALFREDO JARA
Plan Check Approved 4/25/2023 EDWIN ESPIN
Issued 8/7/2023 APPLICANT
Permit Finaled 2/21/2024 MISAEL ESPARZA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/10/2023 MICHAEL TEMPLE
Specific Plan Cleared 4/12/2023 OLGA AYALA
ZA Case Cleared 4/12/2023 YINGSHI HUANG
ZI Cleared 4/12/2023 OLGA AYALA

Contact Information

Architect Lee,, Kenneth David; Lic. No.: C10141 16501 ACADEMIA DRIVE      ENCINO, CA 91436
Architect Lee,, Kenneth David; Lic. No.: NA10141       ,
Contractor Owner-Builder       ,
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 10/2/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 10/12/2023 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/16/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/18/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 10/18/2023 Approved MISAEL ESPARZA
HVAC-Rough 10/18/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/24/2023 Approved MISAEL ESPARZA
HVAC-Rough 10/24/2023 Approved MISAEL ESPARZA
Insulation 10/24/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/7/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 11/14/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/14/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 12/12/2023 Approved ROBERT GOLD
ELECTRICAL-Final 2/15/2024 Corrections Issued MISAEL ESPARZA
Final 2/15/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 2/15/2024 Approved MISAEL ESPARZA
PLUMBING-Final 2/15/2024 Partial Approval MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/15/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/21/2024 Approved MISAEL ESPARZA
Final 2/21/2024 Permit Finaled MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Approved MISAEL ESPARZA