3821 S HOBART BLVD 90062
Certificate Information: 3821 S HOBART BLVD 90062
- Application / Permit
- 23016-10000-07324
- Plan Check / Job No.
- B23LA04471
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: INTERIOR AND EXTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/13/2023
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2023 | DANIEL YIP |
| Corrections Issued | 3/23/2023 | DANIEL YIP |
| Applicant returned to address corrections | 3/28/2023 | DANIEL YIP |
| Plan Check Approved | 4/7/2023 | DANIEL YIP |
| Issued | 4/10/2023 | APPLICANT |
| Permit Finaled | 7/11/2023 | CHARLES BOGHOSKHAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Proud Crowd Inc The; Lic. No.: 1074719-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/12/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/5/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/5/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 5/5/2023 | Approved | SABAS ALONSO |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 5/11/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/11/2023 | Approved | SABAS ALONSO |
| Insulation | 5/17/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/22/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/22/2023 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 5/26/2023 | Approved | SABAS ALONSO |
| Final | 7/11/2023 | Permit Finaled | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | CHARLES BOGHOSKHAN |
| Smoke Detectors | 7/11/2023 | Approved | CHARLES BOGHOSKHAN |