3845 1/2 W ALOHA ST 90027
Certificate Information: 3845 1/2 W ALOHA ST 90027
- Application / Permit
- 23016-10000-07286
- Plan Check / Job No.
- B23LA04465
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN** CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) - WORK PER ENGINEER
- Permit Issued
- Issued on 9/13/2023
- Issuing Office
- Current Status
- CofO Issued on 2/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 3/20/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/27/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 7/11/2023 | OMAR GARNICA |
| Plan Check Approved | 9/13/2023 | OMAR GARNICA |
| Issued | 9/13/2023 | APPLICANT |
| CofO in Progress | 2/6/2025 | ENRIQUE MIRELES |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
| CofO Issued | 2/9/2025 | DEROLD HAUFF |
| Permit Finaled | 2/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2023 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/15/2023 | WALLIE JONG |
| Sewer availability | Cleared | 5/15/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 6/1/2023 | VASIL MIHALEV |
| Construction near power lines | Cleared | 8/14/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/6/2023 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 12/6/2023 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/8/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 12/8/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/22/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 1/8/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | JEFFREY MEAD |
| Pre-Inspection | 3/4/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/7/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/23/2025 | Approved | ENRIQUE MIRELES |
| Final | 1/23/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/23/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/23/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/23/2025 | Approved | ENRIQUE MIRELES |
| Final | 2/5/2025 | OK to Issue CofO | ENRIQUE MIRELES |