3831 S MOTOR AVE 90232
Certificate Information: 3831 S MOTOR AVE 90232
- Application / Permit
- 23016-10000-07260
- Plan Check / Job No.
- B23LA04445
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: One New Ordinary steel moment frame and one- 2 way Special Steel Cantilevered Column
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Current Status
- CofC Issued on 7/18/2025
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | HANS SANTIAGO |
| Corrections Issued | 4/3/2023 | HANS SANTIAGO |
| Quality Review Completed | 4/3/2023 | LIPING TENG |
| Quality Review Completed | 4/12/2023 | CHARLES CHANG |
| Applicant returned to address corrections | 8/18/2023 | HANS SANTIAGO |
| Plan Check Approved | 9/4/2023 | ANDREW SANTIAGO |
| Issued | 4/3/2025 | APPLICANT |
| CofC Issued | 7/18/2025 | HENRY BAGHDASSARIAN |
| OK for CofC | 7/21/2025 | DANIEL VARNUM |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/5/2025 | KORNEL LELEA |
Contact Information
| Contractor | Retrocal; Lic. No.: 985586-B | 4730 WOODMAN AVE SUITE 360 SHERMAN OAKS, CA 91423 |
| Engineer | Labib,, Youhanna T.; Lic. No.: NA4549 | , |
Inspector Information
| DANIEL VARNUM, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/30/2025 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 6/4/2025 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 6/4/2025 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 6/5/2025 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Structural Steel Frame | 6/5/2025 | Approved | DERRICK SPENCER |
| Wood Frame | 6/5/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Steel/Welding | 6/6/2025 | Approved | DERRICK SPENCER |
| Wood Frame | 6/10/2025 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 6/18/2025 | Approved | PAUL DAVIDSON |
| Final | 7/7/2025 | Partial Approval | DANIEL VARNUM |
| METHANE-Final | 7/7/2025 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 7/7/2025 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 7/21/2025 | Conditional Approval | DANIEL VARNUM |
| Final | 7/21/2025 | OK for CofC | DANIEL VARNUM |