3688 S NORTON AVE 90018
Certificate Information: 3688 S NORTON AVE 90018
- Application / Permit
- 23016-10000-07099
- Plan Check / Job No.
- B23LA04309
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR/EXTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING . ALTER (E) CEILING FRAMING , EXTERIOR OPENINGS, PARTITIONS , AND WINDOWS . REROOF , NEW SKYLIGHTS, AND REMODEL.
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/20/2023
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2023 | GEORGE ALVAREZ |
| Corrections Issued | 3/10/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 3/15/2023 | LUKE GONZALES |
| Issued | 3/17/2023 | APPLICANT |
| Permit Finaled | 9/19/2023 | ANTHONY EGSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Doenitz,, Halle; Lic. No.: C91458 | 1010 OWOSSO AVE HERMOSA BEACH, CA 90254 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/11/2023 | Partial Approval | ANTHONY EGSON |
| Pre-Inspection | 4/24/2023 | Partial Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 4/27/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 5/9/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/17/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/18/2023 | Approved | ANTHONY EGSON |
| Underground Mechanical | 5/18/2023 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/19/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/12/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 6/22/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/23/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/23/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | ANTHONY EGSON |
| Insulation | 6/28/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/7/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/12/2023 | Approved | ANTHONY EGSON |
| Service/Power Release | 8/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 9/6/2023 | Approved | ANTHONY EGSON |
| Final | 9/19/2023 | Permit Finaled | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/19/2023 | Approved | ANTHONY EGSON |