10231 W CHARING CROSS ROAD 90024

Certificate Information: 10231 W CHARING CROSS ROAD 90024

Application / Permit
23016-10000-07087
Plan Check / Job No.
B23LA04290
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) INDOOR POOL/SPA/SAUNA/STEAM BASEMENT. NO STRUCTURAL WORK.
Permit Issued
Issued on 6/9/2023
Issuing Office
Metro
Current Status
Permit Finaled on 11/26/2024

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/15/2023 WEIJIAN HUANG
Corrections Issued 3/16/2023 WEIJIAN HUANG
Building Plans Picked Up 3/20/2023 APPLICANT
Plan Check Approved 4/14/2023 MINA HABILI
Issued 6/9/2023 APPLICANT
Permit Finaled 11/25/2024 CHRISTOPHER WILSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Holz Richard Inc; Lic. No.: 294504-B 520 S SEPULVEDA BLVD #407      LOS ANGELES, CA 90049

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 6/20/2023 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/12/2023 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/12/2023 No Access for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/12/2023 No Access for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/12/2023 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/18/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/18/2023 Not Ready for Inspection CHRISTOPHER WILSON
Light Gage Steel Frame 10/18/2023 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 10/18/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/26/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/26/2023 Corrections Issued CHRISTOPHER WILSON
Light Gage Steel Frame 10/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/26/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/2/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/2/2023 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 11/2/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 11/2/2023 Partial Approval CHRISTOPHER WILSON
Shower Pan 11/9/2023 Approved BRENDAN LOONEY
Insulation 11/20/2023 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval CHRISTOPHER WILSON
Gas Test 11/22/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/14/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/22/2023 Partial Approval CHRISTOPHER WILSON
Insulation 1/4/2024 Approved STEPHANIE SWANSON
Drywall Nailing 1/22/2024 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 1/22/2024 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 2/16/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/8/2024 Approved CHRISTOPHER WILSON
Grounding or Bonding 5/20/2024 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/20/2024 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 5/20/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/21/2024 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 5/21/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/5/2024 Approved STEPHANIE SWANSON
Drywall Nailing 6/14/2024 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 6/14/2024 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 8/2/2024 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/14/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 8/14/2024 Approved SEAN HAUPT
Final 11/14/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Final 11/14/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 11/14/2024 Approved CHRISTOPHER WILSON
Final 11/25/2024 Permit Finaled CHRISTOPHER WILSON