8207 W 3RD ST A 90048

Certificate Information: 8207 W 3RD ST A 90048

Application / Permit
23016-10000-06866
Plan Check / Job No.
B23LA04106
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Beauty Shop or Parlor
Work Description
CHANGE OF USE FROM (E) RETAIL STORE TO (N) BEAUTY SHOP. NO CHANGE IN PARKING.
Permit Issued
Issued on 5/11/2023
Issuing Office
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2023 APPLICANT
Assigned to Plan Check Engineer 3/14/2023 GURUNATH NESARAJAH
Corrections Issued 3/15/2023 GURUNATH NESARAJAH
Applicant returned to address corrections 4/4/2023 GURUNATH NESARAJAH
Plan Check Approved 5/10/2023 PINANK PATEL
Issued 5/11/2023 APPLICANT
CofO in Progress 11/20/2023 ERNESTO CORRAL
Permit Finaled 12/6/2023 ADAM BURGESS
CofO Issued 12/6/2023 ADAM BURGESS
Permit Finaled 12/6/2023 ADAM BURGESS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/20/2023 DAVID VO
Sewer availability Cleared 4/20/2023 DAVID VO
Comm Cor/Mini-Mall Cleared 5/4/2023 ASHLEY RODARTE
Comm Cor/Mini-Mall Cleared 5/4/2023 ASHLEY RODARTE
ZA Case Cleared 5/4/2023 ASHLEY RODARTE
Comm Cor/Mini-Mall Cleared 5/8/2023 ASHLEY RODARTE

Contact Information

Architect , ; Lic. No.: C37208       ,
Contractor Pag Construction Inc; Lic. No.: 642785-B       ,
Engineer Lin,, Jason; Lic. No.: S6095 801 CREST VISTA DR      MONTEREY PARK, CA 91754

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 7/7/2023 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 8/8/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Concrete 8/9/2023 Approved ALFREDO LOPEZ
Light Gage Steel Frame 9/8/2023 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 9/12/2023 Not Ready for Inspection ALFREDO LOPEZ
Light Gage Steel Frame 9/13/2023 Partial Approval GREGORY POMISH
Drywall Nailing 9/15/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 9/20/2023 Partial Approval JEROME BLACKWOOD
Final 10/24/2023 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Final 10/24/2023 Approved ALFREDO LOPEZ
METHANE-Rough 10/24/2023 Approved ALFREDO LOPEZ
Reinforced Masonry Frame 10/24/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 10/24/2023 Not Ready for Inspection ALFREDO LOPEZ
T-Bar Ceiling 10/24/2023 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Not Ready JEROME BLACKWOOD
Final 11/20/2023 OK to Issue CofO MARTIN TAVITIAN
Reinforced Masonry Frame 11/20/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV No Gas MARTIN TAVITIAN
Smoke Detectors 11/20/2023 Approved MARTIN TAVITIAN