1718-1718 1/2 W 252ND ST 90717
Certificate Information: 1718-1718 1/2 W 252ND ST 90717
- Application / Permit
- 23016-10000-06854
- Plan Check / Job No.
- B23LA04090
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing Attached 3-Car Garage to Accessory Dwelling Unit per State Law and GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- CofO Issued on 10/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2023 | ZAW HAN |
| Corrections Issued | 4/4/2023 | ZAW HAN |
| Applicant returned to address corrections | 4/24/2023 | ZAW HAN |
| Applicant returned to address corrections | 4/27/2023 | ZAW HAN |
| Applicant returned to address corrections | 5/4/2023 | ZAW HAN |
| Plan Check Approved | 5/24/2023 | GEORGE ALVAREZ |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 10/17/2023 | EUGENE CASSIDY |
| CofO Issued | 10/19/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/19/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/11/2023 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 4/12/2023 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2023 | ANA SORIANO |
| Sewer availability | Cleared | 5/18/2023 | ANA SORIANO |
Contact Information
| Contractor | Doubletree Construction; Lic. No.: 1005059-B | , |
| Engineer | Itani,, Riad Hassan; Lic. No.: C55688 | 2459 W 228TH ST TORRANCE, CA 90501 |
| Engineer | Itani,, Riad Hassan; Lic. No.: NA55688 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2023 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/30/2023 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 6/12/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/12/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/3/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/8/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/8/2023 | Approved | EUGENE CASSIDY |
| Insulation | 8/14/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/14/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 8/14/2023 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/17/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 9/28/2023 | Approved | EUGENE CASSIDY |
| Final | 9/28/2023 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 9/28/2023 | Conditional Approval | EUGENE CASSIDY |
| METHANE-Final | 9/28/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/28/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 9/28/2023 | Approved | EUGENE CASSIDY |
| Final | 10/3/2023 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 10/3/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/16/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/16/2023 | Approved | EUGENE CASSIDY |