1703 S GLYNDON AVE 90291

Certificate Information: 1703 S GLYNDON AVE 90291

Application / Permit
23016-10000-06746
Plan Check / Job No.
B23LA04023
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' x 20' ATTACHED GARAGE TO (N) ATTACHED 400 S.F ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) AND (e). WORK DONE PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 03/09/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/3/2025
Issuing Office
Current Status
CofO Issued on 3/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 MIROOSH KHACHATOORIAN
Corrections Issued 3/18/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 4/7/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 10/1/2023 ROSENDO MEDINA
Issued 2/3/2025 APPLICANT
Permit Finaled 3/16/2026 CLAUDIO MORENO
CofO Issued 3/16/2026 CLAUDIO MORENO
Permit Finaled 3/16/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 3/28/2023 ANA SORIANO
Specific Plan Cleared 3/29/2023 ALESSANDRO MERCURI
Eng Process Fee Ord 176,300 Cleared 4/3/2023 ANA SORIANO
Sewer availability Cleared 4/3/2023 ANA SORIANO
Grading Pre-Inspection Cleared 4/4/2023 MATTHEW JENKINS
Construction near power lines Cleared 8/6/2023 TINA MIRANDA

Contact Information

Contractor Suarez Build Construction Inc; Lic. No.: 1032579-B       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2025 Approved RYAN BARNES
Excavation/Setback/Form/Re-Bar 3/18/2025 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved RYAN BARNES
Insulation 4/25/2025 Partial Approval RYAN BARNES
Insulation 5/2/2025 Corrections Issued ANDREW BEELI
Interior/Exterior Lathing 5/2/2025 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 5/13/2025 Not Ready for Inspection RYAN BARNES
Insulation 5/13/2025 Partial Approval RYAN BARNES
Interior/Exterior Lathing 5/13/2025 Partial Approval RYAN BARNES
PLUMBING-Rough 5/13/2025 Not Ready for Inspection RYAN BARNES
Drywall Nailing 5/27/2025 Approved RYAN BARNES
Pre-Inspection 5/27/2025 Approved RYAN BARNES
Rough-Elec/Plmb/HVAC 5/27/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 6/4/2025 Approved RYAN BARNES
Final 6/4/2025 Not Ready for Inspection RYAN BARNES
Green Building Final 6/4/2025 Approved RYAN BARNES
Green Building Rough 6/4/2025 Approved RYAN BARNES
Smoke Detectors 6/4/2025 Approved RYAN BARNES
Final 7/2/2025 Conditional Approval RYAN BARNES