6330 1/4 S BRYNHURST AVE 90043

Certificate Information: 6330 1/4 S BRYNHURST AVE 90043

Application / Permit
23016-10000-06486
Plan Check / Job No.
B23LA03892
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: convert (e) carport to (n) 1-story ADU per LAMC 12.22 A.33 (c)(d)(g) and GCS 65852.2(e)(1)(D) ADU 1 north side 1 of 2
Permit Issued
Issued on 11/7/2023
Issuing Office
Current Status
CofO Issued on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 KELVIN CHUONG
Corrections Issued 4/6/2023 KELVIN CHUONG
Quality Review Completed 4/11/2023 RODOLFO ARIAS
Applicant returned to address corrections 7/6/2023 KELVIN CHUONG
Applicant returned to address corrections 7/24/2023 KELVIN CHUONG
Plan Check Approved 11/3/2023 KELVIN CHUONG
Issued 11/7/2023 APPLICANT
CofO in Progress 8/22/2025 WAYNE REGESTER
No Progress 8/24/2025 DEROLD HAUFF
CofO in Progress 8/24/2025 DEROLD HAUFF
CofO in Progress 10/1/2025 MICHAEL LEWIS
Permit Finaled 10/1/2025 DEROLD HAUFF
CofO Issued 10/1/2025 DEROLD HAUFF
Permit Finaled 10/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/22/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 5/22/2023 TREVOR QUAN
Sewer availability Cleared 5/22/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/1/2023 TREVOR QUAN
Hydrant and Access approval Cleared 6/13/2023 MATTHEW CRAIG
Miscellaneous Cleared 6/16/2023 TERRY PHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: NA93095       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/11/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 5/2/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 6/17/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Not Ready for Inspection JOSE MACIAS
HVAC-Rough 8/16/2024 Approved JOSE MACIAS
PLUMBING-Rough 8/16/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 8/23/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 8/23/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Approved JOSE MACIAS
Green Building Rough 8/23/2024 Approved JOSE MACIAS
Insulation 8/30/2024 Approved ALEX COLIN
Interior/Exterior Lathing 8/30/2024 Partial Approval ALEX COLIN
Drywall Nailing 9/6/2024 Approved ALEX COLIN
Interior/Exterior Lathing 9/10/2024 Approved AMIR NAZARIAN
Final 5/14/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 5/14/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Not Required WAYNE REGESTER
Smoke Detectors 5/14/2025 Approved WAYNE REGESTER
Final 8/5/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 8/5/2025 Approved WAYNE REGESTER
Final 8/15/2025 Corrections Issued WAYNE REGESTER
Final 8/19/2025 Not Ready for Inspection WAYNE REGESTER
Final 8/21/2025 OK to Issue CofO WAYNE REGESTER