525 N SPOLETO DR 90272

Certificate Information: 525 N SPOLETO DR 90272

Application / Permit
23016-10000-06301
Plan Check / Job No.
B23LA03808
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel only renovate kitchen and bath on second floor with window and door like for like changes. All work per engineer. No addition square footage, no change in overall height.
Permit Issued
Issued on 4/26/2023
Issuing Office
Valley
Current Status
Permit Finaled on 6/27/2024

Permit Application Status History

Submitted 3/3/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 VICTOR CHEN
Corrections Issued 3/14/2023 VICTOR CHEN
Building Plans Picked Up 3/15/2023 APPLICANT
Applicant returned to address corrections 4/11/2023 KHUONG TRUONG
Plan Check Approved 4/14/2023 VICTOR CHEN
Issued 4/26/2023 APPLICANT
Permit Finaled 6/27/2024 ARAM AVEDISIAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/22/2023 KIRK LINKLATER
Miscellaneous Cleared 3/28/2023 RUBEN VASQUEZ
Miscellaneous Cleared 3/28/2023 RUBEN VASQUEZ

Contact Information

Contractor Titan Contracting Inc; Lic. No.: 1065317-B 13317 VENTURA BLVD   STE F1    SHERMAN OAKS, CA 91423
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 6/7/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/12/2023 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 7/19/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 7/19/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 7/25/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/2/2023 Partial Approval OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 9/14/2023 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 9/26/2023 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 9/26/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/12/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 10/12/2023 Approved OGANES TARAKHCHYAN
Insulation 10/12/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 10/12/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/17/2023 Approved ARAM AVEDISIAN
HVAC-Rough 10/17/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/17/2023 Approved ARAM AVEDISIAN
Deputy Drilled-In Anchors 10/31/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 11/7/2023 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 11/14/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued HERBERT GIRON
Insulation 11/14/2023 Corrections Issued HERBERT GIRON
Shower Pan 11/20/2023 Approved ARAM AVEDISIAN
Drywall Nailing 11/22/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/22/2023 Partial Approval ARAM AVEDISIAN
HVAC-Rough 1/9/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/11/2024 Partial Approval ARAM AVEDISIAN
Wood Frame 1/26/2024 Partial Approval MICHAEL PELHAM
Interior/Exterior Lathing 2/13/2024 Partial Approval KENNETH NAGLE
Final 5/30/2024 Partial Inspection ARAM AVEDISIAN
Smoke Detectors 5/30/2024 Approved ARAM AVEDISIAN
Final 6/6/2024 Corrections Issued ARAM AVEDISIAN
Final 6/27/2024 Permit Finaled ARAM AVEDISIAN