3111-3111 1/2 E ATLANTIC ST 90023
Certificate Information: 3111-3111 1/2 E ATLANTIC ST 90023
- Application / Permit
- 23016-10000-06081
- Plan Check / Job No.
- B23LA03610
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. CONVERT (E) ATTACHED GARAGE ON 1ST FLOOR OF SINGLE FAMILY DWELLING INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 05/20/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 9/1/2023
- Issuing Office
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2023 | ALFRED RAMIREZ |
| Corrections Issued | 3/16/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/12/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 7/28/2023 | KEVIN MORALES |
| Issued | 9/1/2023 | APPLICANT |
| CofO Issued | 4/23/2024 | DANIEL SANCHEZ |
| Permit Finaled | 4/23/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Hold | Cleared | 5/9/2023 | MARIA VENDIVIL |
| Address approval | Cleared | 6/27/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | CINDY QI |
| Sewer availability | Cleared | 6/27/2023 | CINDY QI |
| ZI | Cleared | 6/27/2023 | NOAH MCCOY |
| ZI | Cleared | 6/30/2023 | NOAH MCCOY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2023 | Approved | PEDRO SIERRA |
| Footing/Foundation/Slab | 10/5/2023 | Partial Approval | PEDRO SIERRA |
| Footing/Foundation/Slab | 10/20/2023 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 10/26/2023 | Partial Approval | PEDRO SIERRA |
| Green Building Rough | 10/26/2023 | Not Ready for Inspection | PEDRO SIERRA |
| MERV13>=Rough | 10/26/2023 | Not Ready for Inspection | PEDRO SIERRA |
| PLUMBING-Rough | 10/26/2023 | Approved | PEDRO SIERRA |
| Interior/Exterior Lathing | 11/13/2023 | Approved | RAUL VASQUEZ |
| ELECTRICAL-Rough | 11/22/2023 | Approved | PEDRO SIERRA |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | PEDRO SIERRA |
| MERV13>=Rough | 11/22/2023 | Not Ready for Inspection | PEDRO SIERRA |
| PLUMBING-Rough | 11/22/2023 | Approved | PEDRO SIERRA |
| Drywall Nailing | 11/29/2023 | Partial Approval | PEDRO SIERRA |
| Insulation | 11/29/2023 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 11/30/2023 | Partial Approval | PEDRO SIERRA |
| Drywall Nailing | 12/6/2023 | Approved | PEDRO SIERRA |
| Final | 1/29/2024 | Corrections Issued | PEDRO SIERRA |
| MERV13>=Final | 1/29/2024 | Approved | PEDRO SIERRA |
| MERV13>=Rough | 1/29/2024 | Approved | PEDRO SIERRA |
| Smoke Detectors | 1/29/2024 | Corrections Issued | PEDRO SIERRA |
| BUILDING-Rough-Frame | 2/7/2024 | Approved | PEDRO SIERRA |
| ELECTRICAL-Final | 2/7/2024 | Approved | PEDRO SIERRA |
| Final | 2/7/2024 | Corrections Issued | PEDRO SIERRA |
| Green Building Final | 2/7/2024 | Approved | PEDRO SIERRA |
| Green Building Rough | 2/7/2024 | Approved | PEDRO SIERRA |
| HVAC-Final | 2/7/2024 | Approved | PEDRO SIERRA |
| PLUMBING-Final | 2/7/2024 | Approved | PEDRO SIERRA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | No Access for Inspection | PEDRO SIERRA |
| Smoke Detectors | 2/7/2024 | Approved | PEDRO SIERRA |
| Final | 4/22/2024 | Partial Approval | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Approved | DANIEL DELACRUZ |