326 S LESLIE WAY 90042
Certificate Information: 326 S LESLIE WAY 90042
- Application / Permit
- 23016-10000-06042
- Plan Check / Job No.
- B23LA03582
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL TO (E) DUPLEX TO DEMO WALLS, CHANGE FLOOR PLAN, & REFRAME PORTION OF ROOF
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/10/2024
Permit Application Status History
| Submitted | 3/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/6/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 4/7/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 5/22/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 6/14/2023 | ALEC MOUSAKHANIAN |
| Issued | 6/14/2023 | APPLICANT |
| Permit Finaled | 7/9/2024 | LILIANA PORTILLO |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/16/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/16/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | ADRIAN SANCHEZ |
| Grading Pre-Inspection | Cleared | 6/1/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 12/18/2023 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 12/18/2023 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 12/18/2023 | Approved | AMY COLIN |
| MERV13>=Rough | 12/18/2023 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 12/18/2023 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 12/22/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 12/22/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 12/22/2023 | Approved | AMY COLIN |
| Insulation | 1/4/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 1/4/2024 | Partial Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Corrections Issued | AMY COLIN |
| Wood Frame | 1/10/2024 | Not Ready for Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | AMY COLIN |
| Drywall Nailing | 1/24/2024 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/6/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 6/24/2024 | Corrections Issued | LILIANA PORTILLO |
| MERV13>=Final | 6/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Rough | 6/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 6/24/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/1/2024 | Approved | LILIANA PORTILLO |
| Final | 7/1/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Final | 7/1/2024 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 7/1/2024 | Approved | LILIANA PORTILLO |
| Final | 7/9/2024 | Permit Finaled | LILIANA PORTILLO |
| Service/Power Release | 7/9/2024 | Approved | LILIANA PORTILLO |