837-839 E 116TH ST 90059

Certificate Information: 837-839 E 116TH ST 90059

Application / Permit
23016-10000-06009
Plan Check / Job No.
B23LA03566
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED 2-CAR GARAGE TO ADU IN 2-STORY SFD PER STATE LAW ***Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 02/11/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector KEITH EDGHILL at (310)732-4533 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 902402.****
Permit Issued
Issued on 3/30/2023
Issuing Office
Metro
Current Status
Issued on 3/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/1/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 KHUONG TRUONG
Corrections Issued 3/7/2023 KHUONG TRUONG
Building Plans Picked Up 3/10/2023 APPLICANT
Plan Check Approved 3/23/2023 DANIEL SANJUAN
Issued 3/30/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/20/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/20/2023 JEANIE LAM
Sewer availability Cleared 3/20/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/3/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 4/24/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 4/26/2023 Approved JAMES CHAVEZ
Deputy Wood Construction 7/18/2023 Conditional Approval KEITH EDGHILL
Deputy Wood Construction 8/8/2023 Conditional Approval KEITH EDGHILL
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved KEITH EDGHILL
Wood Frame 8/10/2023 Conditional Approval KEITH EDGHILL
BUILDING-Rough-Frame 2/26/2026 Conditional Approval KEITH EDGHILL
Drywall Nailing 2/26/2026 Approved KEITH EDGHILL
ELECTRICAL-Final 2/26/2026 Corrections Issued KEITH EDGHILL
ELECTRICAL-Rough 2/26/2026 Approved KEITH EDGHILL
Final 2/26/2026 Not Ready for Inspection KEITH EDGHILL
Green Building Final 2/26/2026 Corrections Issued KEITH EDGHILL
Green Building Rough 2/26/2026 Approved KEITH EDGHILL
HVAC-Final 2/26/2026 Conditional Approval KEITH EDGHILL
PLUMBING-Final 2/26/2026 Approved KEITH EDGHILL
SGSOV-Seismic Gas S/O Valve 2/26/2026 SGSOV Approved KEITH EDGHILL
Smoke Detectors 2/26/2026 Not Ready for Inspection KEITH EDGHILL
BUILDING-Rough-Frame 3/4/2026 Conditional Approval KEITH EDGHILL
Drywall Nailing 3/4/2026 Approved KEITH EDGHILL
ELECTRICAL-Final 3/4/2026 Approved KEITH EDGHILL
Final 3/4/2026 Partial Inspection KEITH EDGHILL
Green Building Final 3/4/2026 Approved KEITH EDGHILL
HVAC-Final 3/4/2026 Approved KEITH EDGHILL
PLUMBING-Final 3/4/2026 Approved KEITH EDGHILL
Smoke Detectors 3/4/2026 Approved KEITH EDGHILL