837-839 E 116TH ST 90059
Certificate Information: 837-839 E 116TH ST 90059
- Application / Permit
- 23016-10000-06009
- Plan Check / Job No.
- B23LA03566
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED 2-CAR GARAGE TO ADU IN 2-STORY SFD PER STATE LAW ***Code Enforcement Bureau has issued an order. This parcel is eligible for issuance of a 30 day time limit permit (including Building, Electrical, HVAC and Plumbing) with a work description as follows. "COMPLY WITH DEPARTMENT ORDER effective date 02/11/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector KEITH EDGHILL at (310)732-4533 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 902402.****
- Permit Issued
- Issued on 3/30/2023
- Issuing Office
- Metro
- Current Status
- Issued on 3/30/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2023 | KHUONG TRUONG |
| Corrections Issued | 3/7/2023 | KHUONG TRUONG |
| Building Plans Picked Up | 3/10/2023 | APPLICANT |
| Plan Check Approved | 3/23/2023 | DANIEL SANJUAN |
| Issued | 3/30/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/20/2023 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/3/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/24/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/26/2023 | Approved | JAMES CHAVEZ |
| Deputy Wood Construction | 7/18/2023 | Conditional Approval | KEITH EDGHILL |
| Deputy Wood Construction | 8/8/2023 | Conditional Approval | KEITH EDGHILL |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Approved | KEITH EDGHILL |
| Wood Frame | 8/10/2023 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 2/26/2026 | Conditional Approval | KEITH EDGHILL |
| Drywall Nailing | 2/26/2026 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 2/26/2026 | Corrections Issued | KEITH EDGHILL |
| ELECTRICAL-Rough | 2/26/2026 | Approved | KEITH EDGHILL |
| Final | 2/26/2026 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 2/26/2026 | Corrections Issued | KEITH EDGHILL |
| Green Building Rough | 2/26/2026 | Approved | KEITH EDGHILL |
| HVAC-Final | 2/26/2026 | Conditional Approval | KEITH EDGHILL |
| PLUMBING-Final | 2/26/2026 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Approved | KEITH EDGHILL |
| Smoke Detectors | 2/26/2026 | Not Ready for Inspection | KEITH EDGHILL |
| BUILDING-Rough-Frame | 3/4/2026 | Conditional Approval | KEITH EDGHILL |
| Drywall Nailing | 3/4/2026 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 3/4/2026 | Approved | KEITH EDGHILL |
| Final | 3/4/2026 | Partial Inspection | KEITH EDGHILL |
| Green Building Final | 3/4/2026 | Approved | KEITH EDGHILL |
| HVAC-Final | 3/4/2026 | Approved | KEITH EDGHILL |
| PLUMBING-Final | 3/4/2026 | Approved | KEITH EDGHILL |
| Smoke Detectors | 3/4/2026 | Approved | KEITH EDGHILL |