1123 S ORLANDO AVE 90035

Certificate Information: 1123 S ORLANDO AVE 90035

Application / Permit
23016-10000-05896
Plan Check / Job No.
B23LA03485
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' x 18' DETACHED GARAGE TO (N) DETACHED ACCESSRY DWELLING UNIT(331 s.f) PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2023 APPLICANT
Assigned to Plan Check Engineer 3/7/2023 MIROOSH KHACHATOORIAN
Corrections Issued 3/8/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 5/17/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/7/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 7/17/2023 MIROOSH KHACHATOORIAN
Issued 9/19/2023 APPLICANT
CofO in Progress 7/15/2025 SCOTT FINNILA
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/14/2023 CELINA MORENO
Sewer availability Cleared 4/14/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/18/2023 CELINA MORENO
HPOZ Cleared 5/28/2023 JONATHAN KAPLAN
Miscellaneous Cleared 5/28/2023 JONATHAN KAPLAN
Miscellaneous Cleared 5/28/2023 JONATHAN KAPLAN
Miscellaneous Cleared 5/28/2023 JONATHAN KAPLAN
Construction within easement Cleared 6/27/2023 RIDWAN HARDY

Contact Information

Contractor Luxe Development Inc; Lic. No.: 993473-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2023 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/30/2023 Not Ready for Inspection JOSE AVILA
Rough-Elec/Plmb/HVAC 12/27/2023 Partial Approval JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 1/9/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/31/2024 Approved STUART CHAPMAN
ELECTRICAL-Rough 1/31/2024 Approved STUART CHAPMAN
Green Building Rough 1/31/2024 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 1/31/2024 Approved STUART CHAPMAN
METHANE-Rough 1/31/2024 Approved STUART CHAPMAN
PLUMBING-Rough 1/31/2024 Approved STUART CHAPMAN
Insulation 2/6/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 2/6/2024 Approved RONNIE MINDANAO
Drywall Nailing 2/9/2024 No Access for Inspection ARTHUR NEGRETE
Insulation 2/9/2024 No Access for Inspection ARTHUR NEGRETE
Drywall Nailing 2/13/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/13/2024 Not Ready for Inspection STUART CHAPMAN
Shower Pan 2/20/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/28/2024 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/27/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 8/27/2024 Approved ARTHUR NEGRETE
Final 8/27/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 8/27/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 8/27/2024 Approved ARTHUR NEGRETE
HVAC-Final 8/27/2024 Corrections Issued ARTHUR NEGRETE
PLUMBING-Final 8/27/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/27/2024 Approved ARTHUR NEGRETE
Final 9/9/2024 Partial Approval ARTHUR NEGRETE
Green Building Final 9/9/2024 Approved ARTHUR NEGRETE
HVAC-Final 9/9/2024 Approved ARTHUR NEGRETE
Final 7/15/2025 OK to Issue CofO SCOTT FINNILA