1829 S MALCOLM AVE 1-8 90025
Certificate Information: 1829 S MALCOLM AVE 1-8 90025
- Application / Permit
- 23016-10000-05812
- Plan Check / Job No.
- B23LA03444
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan: Convert rear attached Garage to and ADU within existing apartment PER GCS 65852.2(e)(1)(C). (see comments)
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Current Status
- CofO Issued on 10/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | ZAW HAN |
| Corrections Issued | 3/5/2023 | ZAW HAN |
| Applicant returned to address corrections | 3/21/2023 | ZAW HAN |
| Applicant returned to address corrections | 4/10/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 5/11/2023 | SHANGQIN XIE |
| Plan Check Approved | 7/10/2023 | RICARDO RAMIREZ |
| Plan Check Approved | 7/28/2023 | RICARDO RAMIREZ |
| Issued | 8/1/2023 | APPLICANT |
| Permit Finaled | 10/24/2024 | DAVID TSAU |
| Permit Finaled | 10/24/2024 | DAVID TSAU |
| CofO Issued | 10/24/2024 | DAVID TSAU |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/28/2023 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 3/31/2023 | DINAH GARIN |
| Sewer availability | Cleared | 3/31/2023 | DINAH GARIN |
| Address approval | Cleared | 4/5/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 5/8/2023 | SERGIO VALENZUELA |
| Tenant Habitability Plan | Cleared | 6/30/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | H Z S Construction; Lic. No.: 1039476-B | 1720 E GARRY AVE #229 SANTA ANA, CA 92705 |
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/27/2023 | No Access for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 12/1/2023 | Partial Inspection | CASIMIR BRITTON |
| Footing/Foundation/Slab | 12/1/2023 | Partial Inspection | CASIMIR BRITTON |
| Footing/Foundation/Slab | 1/10/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Rough | 1/10/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Rough | 1/10/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 1/10/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Rough | 3/14/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Rough | 3/14/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 3/14/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Wood Construction | 3/28/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | RICARDO ROBLES |
| Green Building Rough | 4/3/2024 | Partial Approval | RICARDO ROBLES |
| METHANE-Rough | 4/3/2024 | Approved | RICARDO ROBLES |
| Green Building Rough | 4/19/2024 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 4/19/2024 | Partial Approval | RICARDO ROBLES |
| Wood Frame | 4/19/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 5/6/2024 | Approved | MICHAEL PETRUSKO |
| Deputy Wood Construction | 5/10/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Wood Frame | 5/14/2024 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 5/20/2024 | No Access for Inspection | GRANT WOODS |
| Drywall Nailing | 5/21/2024 | No Access for Inspection | MICHAEL PETRUSKO |
| Drywall Nailing | 5/30/2024 | Approved | MICHAEL PETRUSKO |
| Final | 8/29/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Green Building Final | 8/29/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 8/29/2024 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 9/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 9/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 9/18/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Green Building Final | 9/18/2024 | Approved | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 9/18/2024 | Approved | MICHAEL PETRUSKO |