5726 N HALBRENT AVE 91411

Certificate Information: 5726 N HALBRENT AVE 91411

Application / Permit
23016-10000-05679
Plan Check / Job No.
B23LA03369
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING EXISTING DETACHED GARAGE TO ADU PER WFPP
Permit Issued
Issued on 3/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2023 APPLICANT
Assigned to Plan Check Engineer 3/6/2023 JOSEPH RAFOLS
Corrections Issued 3/8/2023 JOSEPH RAFOLS
Plan Check Approved 3/21/2023 DANIEL SANJUAN
Issued 3/22/2023 APPLICANT
CofO in Progress 7/14/2023 RYAN SALAZAR
CofO Issued 7/31/2023 RUBEN SALAS
Permit Finaled 7/31/2023 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 3/14/2023 OSCAR CASTRO
Address approval Cleared 3/20/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/20/2023 CHRIS CHAHBAZ
Sewer availability Cleared 3/20/2023 CARLOS AGUILERA

Contact Information

Contractor L A General Construction Co; Lic. No.: 1052200-B 319 N CURTIS AVE APT A      ALHAMBRA, CA 91801

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/13/2023 Approved RYAN SALAZAR
PLUMBING-Rough 4/13/2023 Partial Approval RYAN SALAZAR
Sewer 4/13/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/26/2023 Conditional Approval RYAN SALAZAR
Green Building Rough 4/26/2023 Not Ready for Inspection RYAN SALAZAR
MERV13>=Rough 4/26/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 4/26/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/28/2023 Approved RYAN SALAZAR
HVAC-Rough 4/28/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 5/5/2023 Approved JOHN COLEMAN
Insulation 5/5/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 5/5/2023 Corrections Issued JOHN COLEMAN
Drywall Nailing 5/10/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/10/2023 Approved RYAN SALAZAR
Shower Pan 5/10/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 6/16/2023 Approved RYAN SALAZAR
PLUMBING-Final 6/16/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/22/2023 Approved RYAN SALAZAR
Final 6/22/2023 Corrections Issued RYAN SALAZAR
Green Building Final 6/22/2023 Approved RYAN SALAZAR
Green Building Rough 6/22/2023 Approved RYAN SALAZAR
HVAC-Final 6/22/2023 Approved RYAN SALAZAR
MERV13>=Final 6/22/2023 Approved RYAN SALAZAR
MERV13>=Rough 6/22/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/22/2023 Approved RYAN SALAZAR
Final 6/29/2023 Partial Approval RYAN SALAZAR
Special/Order Compliance 7/10/2023 Corrections Issued RYAN SALAZAR
Final 7/14/2023 OK to Issue CofO RYAN SALAZAR