7868 N VAN NUYS BLVD 91402
Certificate Information: 7868 N VAN NUYS BLVD 91402
- Application / Permit
- 23016-10000-05675
- Plan Check / Job No.
- B23LA03367
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- PROPOSED CHANGE OF USE FROM RESTAURANT TO OFFIC; WORK TO INCLUDE NEW PARTITIONS, CEILING, FINISHES AND MILLWORK
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | SINA KHOSRAVI |
| Corrections Issued | 3/7/2023 | SINA KHOSRAVI |
| Quality Review Completed | 3/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 3/15/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 3/17/2023 | APPLICANT |
| Building Plans Picked Up | 3/21/2023 | APPLICANT |
| Applicant returned to address corrections | 4/21/2023 | SINA KHOSRAVI |
| Plan Check Approved | 5/1/2023 | SINA KHOSRAVI |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 11/30/2023 | ANDREW DORSO |
| Permit Finaled | 12/4/2023 | JEFFREY DURAN |
| CofO Issued | 12/4/2023 | JEFFREY DURAN |
| Permit Finaled | 12/4/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/22/2023 | YINGSHI HUANG |
| ZA Case | Cleared | 3/22/2023 | YINGSHI HUANG |
| Supp. Use District POD/CDO/TDO | Cleared | 3/23/2023 | PEGGY MALONE-BROWN |
| ZA Case | Cleared | 3/23/2023 | PEGGY MALONE-BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 4/7/2023 | COLIN LOREDO |
| Green Code | Cleared | 4/19/2023 | MICHAEL MARTINEZ |
| DAS Clearance | Cleared | 4/27/2023 | SHINE LIN |
Contact Information
| Architect | Munir,, Danette Lene; Lic. No.: C35911 | , |
| Contractor | Sierra Pacific Constructors Inc; Lic. No.: 433163-B | 22212 VENTURA BLVD WOODLAND HILLS, CA 91364 |
| Engineer | Mcdonald,, James Alan; Lic. No.: S4766 | 6 MACAW ALISO VIEJO, CA 92656 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/23/2023 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/27/2023 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/30/2023 | Partial Inspection | ANDREW DORSO |
| Insulation | 7/5/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 7/6/2023 | Partial Approval | DANNY RODRIGUEZ |
| Insulation | 7/10/2023 | Partial Approval | DANNY RODRIGUEZ |
| Drywall Nailing | 7/13/2023 | Approved | KENNETH ROBERTS |
| Light Gage Steel Frame | 7/20/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 7/26/2023 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/28/2023 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 8/15/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 11/6/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 11/6/2023 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 11/6/2023 | Not Ready for Inspection | ANDREW DORSO |
| Final | 11/28/2023 | OK to Issue CofO | ANDREW DORSO |
| Smoke Detectors | 11/28/2023 | Approved | ANDREW DORSO |