1620 S STEARNS DR 90035
Certificate Information: 1620 S STEARNS DR 90035
- Application / Permit
- 23016-10000-05522
- Plan Check / Job No.
- B23LA03294
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan: Fire / Water damage repair throughout (e) duplex. all work per eng.
- Permit Issued
- Issued on 4/27/2023
- Issuing Office
- Current Status
- Issued on 4/27/2023
Permit Application Status History
| Submitted | 3/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/14/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/19/2023 | LUISANGEL VALENZUELA |
| Issued | 4/27/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Vargas Probuild Inc; Lic. No.: 868706-B | , |
| Engineer | Trenbeth,, Charles Stephen; Lic. No.: C68937 | 3074 BEACHCOMBER DR MORRO BAY, CA 93442 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/1/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/13/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 6/23/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/24/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 8/24/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 10/19/2023 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 10/20/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 10/20/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/20/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 2/29/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/29/2024 | Approved | STUART CHAPMAN |
| Gas Test | 2/29/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/29/2024 | Approved | STUART CHAPMAN |