4041 W EDENHURST AVE 90039

Certificate Information: 4041 W EDENHURST AVE 90039

Application / Permit
23016-10000-05435
Plan Check / Job No.
B23LA03240
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) detached 2-car Garage to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work done per engineering.
Permit Issued
Issued on 8/31/2023
Issuing Office
Valley
Current Status
CofO Corrected on 8/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2023 APPLICANT
Assigned to Plan Check Engineer 2/24/2023 DANIEL SMILEY
Corrections Issued 2/24/2023 DANIEL SMILEY
Applicant returned to address corrections 8/4/2023 MICHAEL LANZONE
Plan Check Approved 8/8/2023 MICHAEL LANZONE
Issued 8/31/2023 APPLICANT
CofO in Progress 4/4/2024 HAMIK HARTOUNIAN
CofO Issued-Status Void 4/8/2024 DEROLD HAUFF
Permit Finaled-Status Void 4/8/2024 DEROLD HAUFF
Re-Activate Permit 8/28/2024 RONALD MYRICK
CofO Corrected 8/28/2024 RONALD MYRICK
Permit Finaled 8/28/2024 RONALD MYRICK

Permit Application Clearance Information

ZI Cleared 4/28/2023 DANIEL CORONADO
Address approval Cleared 7/11/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/11/2023 JESSICA OPINION
Sewer availability Cleared 7/11/2023 JESSICA OPINION
Construction near power lines Cleared 8/8/2023 TINA MIRANDA

Contact Information

Contractor Pac Construction Group Inc; Lic. No.: 1062482-B 2219 BURKETT RD      EL MONTE, CA 91732
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 9/26/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/17/2023 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 10/17/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/20/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval SCOTT FINNILA
Underground Mechanical 11/20/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 11/27/2023 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/27/2023 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/27/2023 Approved HAMIK HARTOUNIAN
Shower Pan 11/27/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/30/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/30/2023 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/5/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 12/5/2023 Conditional Approval HAMIK HARTOUNIAN
Insulation 12/5/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/11/2023 Approved HAMIK HARTOUNIAN
Final 2/9/2024 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 2/9/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/21/2024 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV No Gas HAMIK HARTOUNIAN
Smoke Detectors 2/21/2024 Approved HAMIK HARTOUNIAN