4041 W EDENHURST AVE 90039
Certificate Information: 4041 W EDENHURST AVE 90039
- Application / Permit
- 23016-10000-05435
- Plan Check / Job No.
- B23LA03240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) detached 2-car Garage to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work done per engineering.
- Permit Issued
- Issued on 8/31/2023
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | DANIEL SMILEY |
| Corrections Issued | 2/24/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 8/4/2023 | MICHAEL LANZONE |
| Plan Check Approved | 8/8/2023 | MICHAEL LANZONE |
| Issued | 8/31/2023 | APPLICANT |
| CofO in Progress | 4/4/2024 | HAMIK HARTOUNIAN |
| CofO Issued-Status Void | 4/8/2024 | DEROLD HAUFF |
| Permit Finaled-Status Void | 4/8/2024 | DEROLD HAUFF |
| Re-Activate Permit | 8/28/2024 | RONALD MYRICK |
| CofO Corrected | 8/28/2024 | RONALD MYRICK |
| Permit Finaled | 8/28/2024 | RONALD MYRICK |
Permit Application Clearance Information
| ZI | Cleared | 4/28/2023 | DANIEL CORONADO |
| Address approval | Cleared | 7/11/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 7/11/2023 | JESSICA OPINION |
| Construction near power lines | Cleared | 8/8/2023 | TINA MIRANDA |
Contact Information
| Contractor | Pac Construction Group Inc; Lic. No.: 1062482-B | 2219 BURKETT RD EL MONTE, CA 91732 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/26/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/17/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/17/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/20/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 11/20/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/27/2023 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 11/27/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/30/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/30/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/5/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/5/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 12/5/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/11/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 2/9/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/9/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 2/21/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/21/2024 | Approved | HAMIK HARTOUNIAN |