425 S TOWNE AVE 90013
Certificate Information: 425 S TOWNE AVE 90013
- Application / Permit
- 23016-10000-05268
- Plan Check / Job No.
- B23LA03152
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- eplan. Exterior alteration to add new solar panels (electrical work to be done under separate permit)
- Permit Issued
- Issued on 4/1/2024
- Issuing Office
- Current Status
- Permit Finaled on 5/27/2025
Permit Application Status History
| Submitted | 4/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | MINA HABIB |
| Corrections Issued | 5/30/2023 | MINA HABIB |
| Quality Review Completed | 6/2/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/29/2023 | MINA HABIB |
| Applicant returned to address corrections | 11/16/2023 | MINA HABIB |
| Plan Check Approved | 3/29/2024 | MINA HABIB |
| Issued | 4/1/2024 | APPLICANT |
| Permit Finaled | 5/27/2025 | NICK DANERI |
Permit Application Clearance Information
| Green Code | Cleared | 5/10/2023 | Fernando Flores |
| Historic Resource Verification | Cleared | 6/6/2023 | MAX LODER |
| Low Impact Development (LID) | Cleared | 6/6/2023 | MARTIN FRAGOSO |
| "D" conditions | Cleared | 6/8/2023 | JAZMIN ROQUE |
| "Q" conditions | Cleared | 6/8/2023 | JAZMIN ROQUE |
| CPC | Cleared | 6/8/2023 | JAZMIN ROQUE |
| Redevelopment Project Area | Cleared | 6/20/2023 | CARTER HOWE |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/2/2023 | HUGO LOPEZ |
| DAS Clearance | Cleared | 3/5/2024 | ELIZABETH TOMS |
Contact Information
| Contractor | California Solar Integrators Inc; Lic. No.: 1004246-B | , |
| Engineer | Zandieh,, Arash; Lic. No.: C82118 | 3666 SILVER OAK PLACE DANVILLE, CA 94506 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/5/2024 | Partial Inspection | NICK DANERI |
| Final | 5/27/2025 | Permit Finaled | NICK DANERI |
| Green Building Final | 5/27/2025 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | NICK DANERI |
| Smoke Detectors | 5/27/2025 | Approved | NICK DANERI |