1652 3/4 W 254TH ST 90710

Certificate Information: 1652 3/4 W 254TH ST 90710

Application / Permit
23016-10000-05228
Plan Check / Job No.
B22LA26647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE WITH AN ADDTION TO ADU PER MULTIPLE ADU STATE LAW (1-STORY)
Permit Issued
Issued on 10/11/2023
Issuing Office
Current Status
CofO Issued on 4/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 CARLOS MONTES
Corrections Issued 2/23/2023 CARLOS MONTES
Quality Review Completed 3/3/2023 GARO TELMI
Applicant returned to address corrections 5/18/2023 CARLOS MONTES
Plan Check Approved 8/4/2023 CARLOS MONTES
Issued 10/11/2023 APPLICANT
CofO in Progress 4/10/2025 EUGENE CASSIDY
Permit Finaled 4/11/2025 ANSON MAGLASANG
CofO Issued 4/11/2025 ANSON MAGLASANG
Permit Finaled 4/11/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/3/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 7/25/2023 ANA SORIANO
Sewer availability Cleared 8/2/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2024 No Access for Inspection ANSON MAGLASANG
METHANE-Barrier 3/15/2024 No Access for Inspection ANSON MAGLASANG
METHANE-Subgrade 3/15/2024 No Access for Inspection ANSON MAGLASANG
Footing/Foundation/Slab 4/22/2024 Approved EUGENE CASSIDY
METHANE-Barrier 4/22/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 4/22/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/23/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/23/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 7/23/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 7/23/2024 Corrections Issued EUGENE CASSIDY
METHANE-Rough 7/23/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 7/23/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 7/29/2024 Corrections Issued EUGENE CASSIDY
HVAC-Rough 7/29/2024 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 7/29/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/2/2024 Corrections Issued EUGENE CASSIDY
HVAC-Rough 8/2/2024 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 8/2/2024 Not Ready for Inspection EUGENE CASSIDY
Special/Order Compliance 8/2/2024 Partial Inspection BARRY HACHE
ELECTRICAL-Rough 8/12/2024 Approved EUGENE CASSIDY
HVAC-Rough 8/12/2024 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 8/12/2024 Partial Approval EUGENE CASSIDY
Insulation 8/20/2024 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 8/20/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/5/2024 Approved JOSEPH MCGARRY
Insulation 9/5/2024 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 9/16/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/16/2024 Approved JOSEPH MCGARRY
Sewer 12/17/2024 Approved EUGENE CASSIDY
Underground Mechanical 12/23/2024 Approved EUGENE CASSIDY
Underground Mechanical 1/27/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/19/2025 Approved EUGENE CASSIDY
Final 3/19/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 3/19/2025 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 3/19/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV No Gas EUGENE CASSIDY
Smoke Detectors 3/19/2025 Approved EUGENE CASSIDY
Final 4/7/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 4/7/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/9/2025 Approved EUGENE CASSIDY
Final 4/9/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/9/2025 Approved EUGENE CASSIDY
PLUMBING-Final 4/9/2025 Approved EUGENE CASSIDY