1106 1/2 W 22ND ST 90731

Certificate Information: 1106 1/2 W 22ND ST 90731

Application / Permit
23016-10000-04886
Plan Check / Job No.
B23LA02907
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/25/2023
Issuing Office
Current Status
CofO Issued on 5/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 KEVIN MORALES
Corrections Issued 3/2/2023 KEVIN MORALES
Applicant returned to address corrections 4/27/2023 KEVIN MORALES
Plan Check Approved 5/3/2023 KEVIN MORALES
Issued 6/25/2023 APPLICANT
CofO in Progress 5/21/2024 JAMES CHAVEZ
Permit Finaled 5/21/2024 ANSON MAGLASANG
CofO Issued 5/21/2024 ANSON MAGLASANG
Permit Finaled 5/21/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 4/25/2023 ANA SORIANO
Sewer availability Cleared 4/25/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 4/26/2023 ANA SORIANO
Hold Cleared 8/8/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Yassin,, Diaa; Lic. No.: NA56295       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/11/2023 Corrections Issued JAMES CHAVEZ
Underground Mechanical 10/16/2023 Partial Approval JAMES CHAVEZ
Footing/Foundation/Slab 10/19/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 11/27/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 11/27/2023 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/30/2023 Corrections Issued ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 11/30/2023 Approved ANSON MAGLASANG
Insulation 12/5/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 12/12/2023 Approved JAMES CHAVEZ
Drywall Nailing 12/12/2023 Approved JAMES CHAVEZ
Green Building Rough 12/12/2023 Approved JAMES CHAVEZ
Insulation 12/12/2023 Approved JAMES CHAVEZ
Sewer 2/2/2024 Approved JAMES CHAVEZ
Final 4/12/2024 Corrections Issued ANSON MAGLASANG
Green Building Final 4/12/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 4/12/2024 Approved ANSON MAGLASANG
Final 5/13/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Not Ready EUGENE CASSIDY
Final 5/16/2024 Conditional Approval JAMES CHAVEZ
Final 5/16/2024 OK to Issue CofO JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved JAMES CHAVEZ