6702 N ETIWANDA AVE 91335
Certificate Information: 6702 N ETIWANDA AVE 91335
- Application / Permit
- 23016-10000-04885
- Plan Check / Job No.
- B23LA02905
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 18'-3" X 20'-4" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 7/29/2023
- Issuing Office
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 3/6/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/12/2023 | DANIEL ABRAMYAN |
| Issued | 7/29/2023 | APPLICANT |
| CofO in Progress | 11/2/2023 | JEFFREY BULL |
| Permit Finaled | 2/12/2024 | JOHN JANSON |
| CofO Issued | 2/12/2024 | JOHN JANSON |
| Permit Finaled | 2/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/16/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 6/7/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/7/2023 | RIDWAN HARDY |
Contact Information
| Architect | Kim,, Hoejun; Lic. No.: NA37047 | , |
| Contractor | Frank Ticas; Lic. No.: 815284-B | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2023 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 8/7/2023 | Approved | JUSTIN HAWLEY |
| Sewer | 8/7/2023 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 8/7/2023 | Approved | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 8/11/2023 | Conditional Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/28/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 8/28/2023 | Not Ready for Inspection | JEFFREY BULL |
| Deputy Wood Construction | 9/1/2023 | Conditional Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/6/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/6/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 9/6/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/6/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/6/2023 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 9/6/2023 | Approved | JEFFREY BULL |
| Insulation | 9/15/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/20/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/20/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/18/2023 | Corrections Issued | JEFFREY BULL |
| Final | 10/18/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 10/18/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 10/18/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/18/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 10/18/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 10/23/2023 | Corrections Issued | HENRY KIM |
| Final | 10/23/2023 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 11/1/2023 | Approved | JEFFREY BULL |
| Final | 11/1/2023 | OK to Issue CofO | JEFFREY BULL |