3628 S MIDVALE AVE 90034
Certificate Information: 3628 S MIDVALE AVE 90034
- Application / Permit
- 23016-10000-04618
- Plan Check / Job No.
- B23LA02748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN. CONVERT PORTIONS OF (E) ATTACHED CARPORT INTO 4 ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(C). C OF O TO BE ISSUED ALONGSIDE: 23016-10000-04522
- Permit Issued
- Issued on 9/7/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | KEVIN MORALES |
| Corrections Issued | 3/6/2023 | KEVIN MORALES |
| Quality Review Completed | 3/7/2023 | EUGENE BARBEAU |
| Plan Check Approved | 8/24/2023 | KEVIN MORALES |
| Issued | 9/7/2023 | APPLICANT |
| CofO in Progress | 2/24/2026 | FARHAD DADBIN |
| Permit Finaled | 3/2/2026 | VASIL MIHALEV |
| CofO Issued | 3/2/2026 | VASIL MIHALEV |
| Permit Finaled | 3/2/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/15/2023 | ALESSANDRO MERCURI |
| Address approval | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Sewer availability | Cleared | 3/16/2023 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 5/24/2023 | MATTHEW CRAIG |
| Fire Marshal Fire Life Safety | Cleared | 7/24/2023 | RONILO MULAWIN |
| Green Code | Cleared | 8/2/2023 | Rosendo Medina |
| DAS Clearance | Cleared | 8/14/2023 | Rosendo Medina |
| Grading Pre-Inspection | Cleared | 8/24/2023 | KEVIN MORALES |
Contact Information
| Contractor | C A S - Concrete Asphalt Specialists Inc; Lic. No.: 995442-B | , |
| Contractor | Cas - Building Specialists Inc; Lic. No.: 995442-B | , |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/14/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/14/2023 | Conditional Approval | FARHAD DADBIN |
| Light Gage Steel Frame | 11/14/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Masonry Wall/Backfill | 11/14/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Piling/Pier/Caisson | 11/14/2023 | Partial Approval | FARHAD DADBIN |
| Reinforced Concrete Frame | 11/14/2023 | Conditional Approval | FARHAD DADBIN |
| Reinforced Masonry Frame | 11/14/2023 | Partial Approval | FARHAD DADBIN |
| Structural Steel Frame | 11/14/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wall Anchors | 11/14/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Masonry Wall/Backfill | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Piling/Pier/Caisson | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Concrete Frame | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Masonry Frame | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Structural Steel Frame | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wall Anchors | 11/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Steel/Welding | 12/1/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 12/1/2023 | Approved | FARHAD DADBIN |
| Deputy Reinf. Concrete | 12/5/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 12/8/2023 | Approved | FARHAD DADBIN |
| Green Building Rough | 12/20/2023 | Approved | MICHAEL PETRUSKO |
| Wall Anchors | 12/20/2023 | Approved | MICHAEL PETRUSKO |
| Wood Frame | 12/20/2023 | Approved | MICHAEL PETRUSKO |
| Deputy Wood Construction | 12/26/2023 | Conditional Approval | FARHAD DADBIN |
| Wall Anchors | 1/5/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wall Anchors | 1/9/2024 | Approved | MICHAEL PETRUSKO |
| Interior/Exterior Lathing | 1/19/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 2/28/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 3/27/2024 | Approved | FARHAD DADBIN |
| Drywall Nailing | 4/1/2024 | Approved | FARHAD DADBIN |
| Special/Order Compliance | 5/14/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 7/19/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 7/19/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 7/19/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 2/5/2026 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/5/2026 | Approved | FARHAD DADBIN |