3628 S MIDVALE AVE 90034

Certificate Information: 3628 S MIDVALE AVE 90034

Application / Permit
23016-10000-04618
Plan Check / Job No.
B23LA02748
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePLAN. CONVERT PORTIONS OF (E) ATTACHED CARPORT INTO 4 ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(C). C OF O TO BE ISSUED ALONGSIDE: 23016-10000-04522
Permit Issued
Issued on 9/7/2023
Issuing Office
Current Status
CofO Issued on 3/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 KEVIN MORALES
Corrections Issued 3/6/2023 KEVIN MORALES
Quality Review Completed 3/7/2023 EUGENE BARBEAU
Plan Check Approved 8/24/2023 KEVIN MORALES
Issued 9/7/2023 APPLICANT
CofO in Progress 2/24/2026 FARHAD DADBIN
Permit Finaled 3/2/2026 VASIL MIHALEV
CofO Issued 3/2/2026 VASIL MIHALEV
Permit Finaled 3/2/2026 VASIL MIHALEV

Permit Application Clearance Information

Specific Plan Cleared 3/15/2023 ALESSANDRO MERCURI
Address approval Cleared 3/16/2023 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 3/16/2023 CATHERINE ADROVER
Sewer availability Cleared 3/16/2023 CATHERINE ADROVER
Hydrant and Access approval Cleared 5/24/2023 MATTHEW CRAIG
Fire Marshal Fire Life Safety Cleared 7/24/2023 RONILO MULAWIN
Green Code Cleared 8/2/2023 Rosendo Medina
DAS Clearance Cleared 8/14/2023 Rosendo Medina
Grading Pre-Inspection Cleared 8/24/2023 KEVIN MORALES

Contact Information

Contractor C A S - Concrete Asphalt Specialists Inc; Lic. No.: 995442-B       ,
Contractor Cas - Building Specialists Inc; Lic. No.: 995442-B       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2023 Not Ready for Inspection FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 11/14/2023 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 11/14/2023 Conditional Approval FARHAD DADBIN
Light Gage Steel Frame 11/14/2023 Not Ready for Inspection FARHAD DADBIN
Masonry Wall/Backfill 11/14/2023 Not Ready for Inspection FARHAD DADBIN
Piling/Pier/Caisson 11/14/2023 Partial Approval FARHAD DADBIN
Reinforced Concrete Frame 11/14/2023 Conditional Approval FARHAD DADBIN
Reinforced Masonry Frame 11/14/2023 Partial Approval FARHAD DADBIN
Structural Steel Frame 11/14/2023 Not Ready for Inspection FARHAD DADBIN
Wall Anchors 11/14/2023 Not Ready for Inspection FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Masonry Wall/Backfill 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Piling/Pier/Caisson 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Reinforced Concrete Frame 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Reinforced Masonry Frame 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Structural Steel Frame 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Wall Anchors 11/16/2023 Not Ready for Inspection FARHAD DADBIN
Deputy Steel/Welding 12/1/2023 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 12/1/2023 Approved FARHAD DADBIN
Deputy Reinf. Concrete 12/5/2023 Conditional Approval FARHAD DADBIN
Footing/Foundation/Slab 12/8/2023 Approved FARHAD DADBIN
Green Building Rough 12/20/2023 Approved MICHAEL PETRUSKO
Wall Anchors 12/20/2023 Approved MICHAEL PETRUSKO
Wood Frame 12/20/2023 Approved MICHAEL PETRUSKO
Deputy Wood Construction 12/26/2023 Conditional Approval FARHAD DADBIN
Wall Anchors 1/5/2024 Not Ready for Inspection FARHAD DADBIN
Wall Anchors 1/9/2024 Approved MICHAEL PETRUSKO
Interior/Exterior Lathing 1/19/2024 Partial Approval FARHAD DADBIN
Insulation 2/28/2024 Partial Approval FARHAD DADBIN
Insulation 3/27/2024 Approved FARHAD DADBIN
Drywall Nailing 4/1/2024 Approved FARHAD DADBIN
Special/Order Compliance 5/14/2024 Not Ready for Inspection FARHAD DADBIN
Final 7/19/2024 Not Ready for Inspection FARHAD DADBIN
Green Building Final 7/19/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 7/19/2024 Not Ready for Inspection FARHAD DADBIN
Final 2/5/2026 OK to Issue CofO FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved FARHAD DADBIN
Smoke Detectors 2/5/2026 Approved FARHAD DADBIN