7250 W MELROSE AVE 90046
Certificate Information: 7250 W MELROSE AVE 90046
- Application / Permit
- 23016-10000-04600
- Plan Check / Job No.
- B23LA02731
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- eplan THE RENOVATION OF THE EXTERIOR FACADE WITH THE ADDITION OF A NEW ARCHITECTURAL FACADE WALL AND NEW ROOF STEEL TRELLIS
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Current Status
- Permit Finaled on 9/10/2024
Permit Application Status History
| Submitted | 2/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | KAVIAN REFAHI |
| Corrections Issued | 3/5/2023 | KAVIAN REFAHI |
| Quality Review Completed | 3/6/2023 | CHIHARU SUZUKI |
| Plan Check Approved | 5/9/2023 | KAVIAN REFAHI |
| Issued | 5/11/2023 | APPLICANT |
| Permit Finaled | 9/10/2024 | MARTIN TAVITIAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/3/2023 | RYAN LY |
| ZA Case | Cleared | 5/3/2023 | RYAN LY |
| DAS Clearance | Cleared | 5/4/2023 | Rosendo Medina |
Contact Information
| Architect | Corona,, Victor M; Lic. No.: C25767 | 25725 WALLACE PLACE STEVENSON RANCH, CA 91381 |
| Contractor | Owner-Builder | , |
| Engineer | Nastarin,, Hooman; Lic. No.: C62199 | 554 S SAN VICNETE BLVD 202 LOS ANGELES, CA 90048 |
| Engineer | Nastarin,, Hooman; Lic. No.: NA62199 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2023 | No Access for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 9/7/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 9/12/2023 | Conditional Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/6/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Structural Steel Frame | 11/6/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Deputy Steel/Welding | 11/8/2023 | Conditional Approval | RICARDO ROBLES |
| Special/Order Compliance | 11/13/2023 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 11/14/2023 | Partial Approval | ALFREDO LOPEZ |
| Structural Steel Frame | 11/14/2023 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 11/15/2023 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 12/20/2023 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 12/27/2023 | Partial Approval | MARTIN TAVITIAN |
| Final | 8/22/2024 | Conditional Approval | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Not Required | MARTIN TAVITIAN |
| Smoke Detectors | 8/22/2024 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 8/29/2024 | Approved | MARTIN TAVITIAN |
| Final | 9/10/2024 | Permit Finaled | MARTIN TAVITIAN |