13306 S VERMONT AVE 90247
Certificate Information: 13306 S VERMONT AVE 90247
- Application / Permit
- 23016-10000-04322
- Plan Check / Job No.
- B23LA02569
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT-STORY OPEN FRONT PARKING GARAGE WITH LIVING UNITS ABOVE. ADD (N)-(1) SPECIAL CANTILEVERED COLUMN
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- CofC Issued on 7/19/2023
Permit Application Status History
| Submitted | 2/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | HANS SANTIAGO |
| Corrections Issued | 3/6/2023 | HANS SANTIAGO |
| Quality Review Completed | 3/13/2023 | LIPING TENG |
| Plan Check Approved | 3/31/2023 | ANDREW SANTIAGO |
| Issued | 5/9/2023 | APPLICANT |
| OK for CofC | 7/19/2023 | JOEY BUCHANAN |
| CofC Issued | 7/19/2023 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/1/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2023 | Approved | AMANUEL BERHE |
| Pre-Inspection | 6/14/2023 | Approved | AMANUEL BERHE |
| Structural Steel Frame | 6/14/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 6/14/2023 | Approved | AMANUEL BERHE |
| Drywall Nailing | 6/16/2023 | Approved | AMANUEL BERHE |
| Final | 6/22/2023 | Corrections Issued | AMANUEL BERHE |
| METHANE-Final | 6/22/2023 | Approved | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Not Ready | AMANUEL BERHE |
| Smoke Detectors | 6/22/2023 | Approved | AMANUEL BERHE |
| Final | 7/11/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 7/19/2023 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | JOEY BUCHANAN |