1430 S SHERBOURNE DR 90035

Certificate Information: 1430 S SHERBOURNE DR 90035

Application / Permit
23016-10000-04321
Plan Check / Job No.
B23LA02568
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (2) HARDY FRAMES STRONG WALLS W/ GRADE BEAM.**CERTIFICATE OF COMPLIACNE FOR SOFT STORY SHALL NOT BE ISSUED TILL CERTIFICATE OF OCCUPANCY FOR ADU PERMIT 23016-10000-07154 IS OBTAINED**
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
CofC Issued on 6/17/2025

Permit Application Status History

Submitted 2/15/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 JESSE VIDUYA
Corrections Issued 3/16/2023 JESSE VIDUYA
Quality Review Completed 3/30/2023 HANS SANTIAGO
Applicant returned to address corrections 4/24/2023 JESSE VIDUYA
Plan Check Approved 5/25/2023 JESSE VIDUYA
Issued 6/11/2024 APPLICANT
OK for CofC 6/13/2025 DARRYL ARNOLD
CofC Issued 6/17/2025 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/5/2024 RICARDO BOHORQUEZ

Contact Information

Contractor Ponderosa Pines Gen Contractors; Lic. No.: 450947-B       ,
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2024 Partial Approval JACOB MYERS
Footing/Foundation/Slab 6/21/2024 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 6/24/2024 Not Ready for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 6/27/2024 Partial Approval JACOB MYERS
Insulation 11/4/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 11/4/2024 Corrections Issued DARRYL ARNOLD
Final 3/27/2025 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 3/27/2025 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/27/2025 Conditional Approval DARRYL ARNOLD
Final 6/13/2025 OK for CofC DARRYL ARNOLD
METHANE-Final 6/13/2025 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV No Gas DARRYL ARNOLD
Smoke Detectors 6/13/2025 Approved DARRYL ARNOLD