1227 E ELM ST 90291

Certificate Information: 1227 E ELM ST 90291

Application / Permit
23016-10000-03938
Plan Check / Job No.
B23LA02400
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Detached 2-Story Building 1st Floor Garage Conversion to ADU per GCS 65852.2 (e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 01/24/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/18/2023
Issuing Office
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2023 APPLICANT
Assigned to Plan Check Engineer 2/24/2023 DAVID CASTILLO
Corrections Issued 2/26/2023 DAVID CASTILLO
Applicant returned to address corrections 3/23/2023 DAVID CASTILLO
Applicant returned to address corrections 4/20/2023 DAVID CASTILLO
Plan Check Approved 6/29/2023 EDWIN ESPIN
Issued 7/18/2023 APPLICANT
CofO in Progress 7/30/2024 JOHN MATTILLO
Permit Finaled 11/21/2024 CLAUDIO MORENO
CofO Issued 11/21/2024 CLAUDIO MORENO
Permit Finaled 11/21/2024 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 3/10/2023 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 4/12/2023 AHMED AMARRAGY
Sewer availability Cleared 4/12/2023 AHMED AMARRAGY
Specific Plan Cleared 4/18/2023 ALESSANDRO MERCURI

Contact Information

Contractor Owner-Builder       ,
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/24/2023 Not Ready for Inspection RYAN BARNES
Final 8/24/2023 Not Ready for Inspection RYAN BARNES
Green Building Final 8/24/2023 Not Ready for Inspection RYAN BARNES
Green Building Rough 8/24/2023 Not Ready for Inspection RYAN BARNES
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready RYAN BARNES
Smoke Detectors 8/24/2023 Not Ready for Inspection RYAN BARNES
Pre-Inspection 5/1/2024 Partial Inspection RYAN BARNES
Footing/Foundation/Slab 5/8/2024 Approved RYAN BARNES
Interior/Exterior Lathing 5/8/2024 Approved RYAN BARNES
Rough-Elec/Plmb/HVAC 5/8/2024 Partial Approval RYAN BARNES
Wood Frame 5/8/2024 Conditional Approval RYAN BARNES
HVAC-Rough 5/15/2024 Approved RYAN BARNES
Insulation 5/15/2024 Approved RYAN BARNES
Sewer 5/15/2024 Not Ready for Inspection RYAN BARNES
Sewer 5/21/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 7/9/2024 Approved JOHN MATTILLO
Final 7/9/2024 Corrections Issued JOHN MATTILLO
Green Building Final 7/9/2024 Approved JOHN MATTILLO
Green Building Rough 7/9/2024 Approved JOHN MATTILLO
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Approved JOHN MATTILLO
Smoke Detectors 7/9/2024 Approved JOHN MATTILLO
Final 7/30/2024 OK to Issue CofO JOHN MATTILLO